Draft regulationDated 28 Sep 2023MSERC/Green Tariff/Regn/2023/208 dated 28.09.2023

Draft

A proposal that has since been finalised as the Terms and Conditions of Green Energy Open Access Regulations, 2023.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on mserc.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

The document is a consultation package: a two-page discussion paper from the Meghalaya State Electricity Regulatory Commission followed by Annexure-A, a full draft regulation dated 28.09.2023 (p1, p3-22). The discussion paper explains that the Commission proposes to use its Electricity Act powers to make green energy open access regulations, in light of the Ministry of Power's 2022 Green Energy Open Access Rules. It summarises the central rules' features — the 100 kW eligibility threshold, discom supply of green power, time-bound approvals, charge certainty, uniform RPO including green hydrogen/ammonia, and green certificates — and notes that the existing 2012 open access regulations remain in force (p1-2).

Annexure-A is the operative draft. Chapter 1 (p3-6) sets title, extent to Meghalaya, commencement on Gazette notification, an objective of providing methodology for open access and banking charges, and definitions. Chapter 2 (p7-11) deals with general open access: categories by duration, eligibility at 100 kW and above with conditions for independent feeders, group consumers and 11 kV connections; nodal agencies (SLDC for short term, STU for medium/long term); application through the central portal, a deemed-approval timeline, priority for long-term and non-fossil sources, appeals to the Commission; monthly banking of surplus green energy with TOD restrictions and lapse of unused credit; and yearly green certificates from the distribution licensee.

Chapter 3 (p12-17) specifies the charge heads: transmission, wheeling, cross-subsidy surcharge, standby, banking and other SLDC/scheduling/deviation charges. It gives cost-based formulas for transmission and wheeling charges, treats dedicated systems, provides for loss factors, sets the CSS formula and caps, exempts certain captive and waste-to-energy cases, and describes standby charges and collection/disbursement through the State Nodal Agency. Chapter 4 (p18) contains directions, relaxation, amendment, difficulty-removal and interpretation powers.

The draft is for comments; it is not stated as notified, and its commencement date depends on the Gazette (p3).

Standard name
Green Energy Open Access Regulations
Primary topics
Green energy open access, Open access charges, Energy banking

Read with this

One more document belongs here and is not on Voltaic: a procedure or order made under it not held as English text.

Voltaic last read MSERC's website for final documents on 26 Nov 2026 and for drafts on 21 Nov 2026. A document MSERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on mserc.gov.in ↗

Report an issue with this document