UERC · Uttarakhand Electricity Regulatory Commission
RE Tariff and Other Terms for Supply of Electricity (First Amendment) Regulations, 2023
UERC (Tariff and Other Terms for Supply of Electricity from Renewable Energy Sources and non-fossil fuel based Co-generating Stations) (First Amendment) Regulations, 2023
AmendmentDated 21 Mar 2023No. F-9(28)(i)/RG/UERC/2023/1527 dated March 21, 2023
Replaced by RE and Non-Fossil Fuel Co-generation Tariff Regulations, 2023
See that regulation for the date it took effect and for anything it keeps in force.
Amends the RE and Non-fossil Fuel Co-generation Tariff Regulations, 2018.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is a short, single-purpose instrument: the Uttarakhand Electricity Regulatory Commission, by notification dated 21 March 2023, substitutes Regulation 9 of its 2018 renewable energy tariff regulations in full, restating the State's Renewable Purchase Obligation framework (p1).
Clause 1 names the amendment, brings it into force on the notification date, and gives it a life of five years from the commencement of the Principal Regulations unless reviewed earlier or extended (p1).
The substituted Regulation 9 obliges "Obligated Entities" — all existing and future distribution licensees, captive users and open access customers in the State — to procure a minimum share of their own consumption from eligible RE sources (p1). The obligation is split into three tracks — Wind RPO, Hydro Purchase Obligation and Other RPO — with a year-by-year trajectory (p1). Each track is tied to asset commissioning cut-offs: wind only from projects commissioned after 31 March 2022, hydro (including pumped storage and small hydro) only from projects commissioned after 8 March 2019, and Other RPO from anything else (p2). The denominator — total energy for own consumption — is defined separately for discoms, open access consumers and captive users (p2).
Provisos let a discom meet HPO out of free power received from post-2019 hydro projects, excluding Local Area Development contributions, and allow a shortfall in one category to be made up from excess in another (p2). Rooftop and small solar generation by non-obligated entities can be counted by the discom toward Other RPO (p2).
A new Energy Storage Obligation is introduced as a rising percentage of total consumption in energy terms from 2023-24 to 2029-30, creditable only where at least 85% of stored energy is from RE sources and counting toward the overall RPO (p3). UREDA is made custodian of RPO compliance data (p3).
Read with this
The regulation
- Dated 6 Sep 2018RE and Non-fossil Fuel Co-generation Tariff Regulations, 2018
Commencement notices and reasons
2 more documents belong here and are not on Voltaic: 2 copies in another language.
Voltaic last read UERC's website for final documents on 24 Nov 2026. A document UERC issued after the page that lists it was read may not be held by Voltaic yet.