Recovery of Expenses and Other Charges for Providing Electric Line or Plant (Revision-II) Regulations, 2022 — Second Amendment, 2026

SECOND AMENDMENT TO MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION (RECOVERY OF EXPENSES AND OTHER CHARGES FOR PROVIDING ELECTRIC LINE OR PLANT USED FOR THE PURPOSE OF GIVING SUPPLY) REGULATIONS (REVISION-II), 2022

AmendmentDated 13 Oct 2026No 1782 /MPERC/2026 dated 13th October 2026

Amends the Recovery of Expenses and other Charges for providing Electric Line or Plant for Supply (Revision-II) Regulations, 2022.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on mperc.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the Second Amendment to the MPERC (Recovery of expenses and other charges for providing electric line or plant used for the purpose of giving supply) Regulations (Revision-II), 2022 — the Commission's rules on what a consumer pays when a licensee lays a line or plant to give supply. It is issued by the Madhya Pradesh Electricity Regulatory Commission at Bhopal on 13 October 2026 under s.181 read with s.45(3)(b) and s.46 of the Electricity Act, 2003 (p3).

Clause 1 gives the short title and provides commencement from the date of publication in the Madhya Pradesh Gazette (p3). Clause 2 substitutes Regulation 4.3.3 of the Principal Regulations, imposing Supply Affording Charges at Rs. 1260 per kVA or part of contract demand on consumers, and — for consumers at 33 kV and above — splitting that charge so that Rs. 1100 per kVA is remitted by the consumer directly to the Transmission Licensee to part-finance system infrastructure development at EHT sub-stations (p3).

Clause 3 substitutes Item IV(c) of Annexure I, the Schedule of Other Charges. It governs supervision charges for shifting electric lines, poles and sub-stations for National Highway construction under Bharat Mala Pariyojna, and for projects of national importance or wider public interest, with different rates depending on whether the work is executed by the Developer or the Owner (p3–4). The substituted table on p4 sets those rates by project category.

The document is short and purely operative. Its audience is distribution and transmission licensees in Madhya Pradesh, consumers taking new or augmented supply on contract demand (especially HT/EHT consumers), and parties executing line-shifting works for highway projects.

Standard name
Recovery of Expenditure and Miscellaneous Charges
Primary topics
Connection and miscellaneous charges

Read with this

Voltaic last read MPERC's website for final documents between 24 Nov 2026 and 26 Nov 2026 (4 pages). A document MPERC issued after the page that lists it was read may not be held by Voltaic yet.