Recovery of Expenses and Other Charges for Providing Electric Line or Plant (Revision-II) Regulations, 2022 — First Amendment, 2025
Madhya Pradesh Electricity Regulatory Commission (Recovery of expenses and other charges for providing electric line or plant used for the purpose of giving supply) (Revision-II) Regulations, 2022 (First amendment) {ARG-31(II)(i) of 2025}
AmendmentDated 27 Mar 2025No 571/MPERC/2025 dated 27.03.2025
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is the First Amendment to MPERC's Revision-II 2022 regulations on recovery of expenses and other charges for providing electric line or plant used for giving supply. Issued as Notification No 571/MPERC/2025 dated 27.03.2025 under s.181 read with s.45(3)(b) and s.46 of the Electricity Act, it takes effect from Gazette publication, which the text does not date (p1).
Section 2 rewrites the Principal Regulations' definitions: it adds a 'Consumer' definition broken into LT, HT and EHT categories by voltage of supply, defines 'Electrified area' by presence of a distribution system in the vicinity of applicants, ties 'Sanctioned load' to the MP Electricity Supply Code, 2021, and replaces 'Connected load' with 'Sanctioned load/Contract demand, as the case may be' (p1–2).
Section 3 reworks how charges are levied: recovery in advance before service, conversion of load between kW and kVA at fixed power factors for LT and HT, an incremental-charge formula for load enhancement, full higher-voltage charges on voltage switchover, and load estimation/limits governed by the Supply Code (p2–3).
Section 4 is the core. It inserts alternative per-kW Supply Affording Charges schedules that an applicant in an electrified area may pay instead of actual-cost recovery, covering several connection/load-size bands and giving BPL applicants their own slabs; sets who bears Distribution Transformer and HT line extension cost above and below a 50 kW threshold, with EV charging stations exempted; allows applicants to lay HT lines themselves against supervision charges; and restates load estimation for non-domestic, industrial and multi-consumer complexes (p3–7).
Section 5 adds an entry to the Annexure I Schedule of Other Charges for check power quality meter rent/installation, with the amount to be issued separately by order (p7).
Read with this
The regulation
Amendments and corrections
One more document belongs here and is not on Voltaic: a copy in another language.
Voltaic last read MPERC's website for final documents between 24 Nov 2026 and 26 Nov 2026 (4 pages). A document MPERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.