CSERC · Chhattisgarh State Electricity Regulatory Commission
Rooftop PV Solar Power Projects Tariff Regulations, 2013
Chhattisgarh State Electricity Regulatory Commission (Determination of tariff for procurement of power from Rooftop PV Solar Power Projects by distribution licensees of State) Regulations, 2013
RegulationDated 7 Oct 2013No. 52/CSERC/2013 dated October 7, 2013
1 amendment to it is on Voltaic, dated 16 Jun 2017.
A later regulation on Voltaic changes some of its provisions: Grid Interactive Distributed Renewable Energy Sources Regulations, 2019.
Summary
Summary written by software. Check the regulator's original before you rely on it.
Notification No. 52/CSERC/2013, dated 7 October 2013, sets the terms on which Chhattisgarh's distribution licensees buy power from rooftop and small ground-mounted solar PV projects. The preamble places it under the Jawaharlal Nehru National Solar Mission and the Electricity Act's renewable-energy mandate, and states it is made under sections 61 and 86 read with section 181 (p1–2). Regulation 1 brings it into force on publication in the Official Gazette; the Gazette date is not printed (p2).
Regulation 2 defines the working vocabulary — solar meter, grid meter, consumer meter, inter-connection point below 33 kV, installed capacity, existing project, useful life, financial year, and the State Agency as CREDA (p2–3). Regulation 3 confines the regulation to tariffs the Commission determines under section 62 read with section 86, subject to the eligibility criteria (p3).
The bulk of the text is Regulation 4's eligibility regime (p4–7): IEC/BIS-compliant modules and inverters, a project-size window centred on 50 kW up to 1 MW, connection to the distribution network at 33 kV or below, CEA-compliant metering with separate solar and grid meters, a communications, SCADA and data-logging duty, power-quality and protection requirements, and a manual disconnection switch. Off-grid JNNSM phase-1 plants with central or state capital assistance, and projects qualifying as captive generating plants, are folded in on their own terms (p6–7).
Regulation 5 fixes a three-year control period, 01.04.2013 to 31.03.2016 (p7), and Regulation 6 a 25-year tariff period from commercial operation, with existing projects timed by mutual agreement (p7). Regulation 7 sets the applicable tariff as half of the generic levellised solar PV tariff for the relevant year under Chapter 7 of the 2012 RE tariff regulations; for FY 2013-14 it records Rs. 4.35 per kWh' on the strength of the Commission's 3 May 2013 suo-motu order, with later CoDs left to subsequent orders (p7–8).
Regulation 8 gives the billing mechanics between licensee, consumer and developer, including a captive-use floor and a cap on energy injected to the grid; Regulation 9 a monthly late payment surcharge; Regulation 10 ties RPO credit to the quantum actually paid for; Regulation 11 a power to remove difficulties by order (p8–9).
Read with this
Amendments and corrections
- Dated 16 Jun 2017Determination of Tariff for Procurement of Power from Rooftop PV Solar Projects (First Amendment) Regulations, 2016
- Dated 4 Oct 2019Changes some provisions: Grid Interactive Distributed Renewable Energy Sources Regulations, 2019
2 more documents belong here and are not on Voltaic: 2 copies in another language.
Voltaic last read CSERC's website for final documents on 24 Nov 2026 and for drafts on 21 Nov 2026. A document CSERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.