Grid Interactive Renewable Energy Systems Related Matters Regulations [Revision-II], 2024 — First Amendment, 2026

Madhya Pradesh Electricity Regulatory Commission (Grid Interactive Renewable Energy Systems Related Matters) Regulations [Revision-II], 2024(First Amendment) [ARG-39(II)(i) of 2026]

Amendment · Gazette copyDated 18 Jun 2026No.1016/MPERC/2026/ dated 18th June 2026

The Gazette copy of the Grid Interactive Renewable Energy Systems Related Matters Regulations [Revision-II], 2024 — First Amendment, 2026.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on mperc.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the First Amendment to MPERC's Grid Interactive Renewable Energy Systems Related Matters Regulations [Revision-II], 2024, issued from Bhopal on 18 June 2026 (p5). It is short: it adds a definition, inserts three provisos into Regulation 6, makes two small textual substitutions in Regulation 8, and substitutes Regulation 9 in full (p5–7). The document says it comes into force from the date of publication in the Madhya Pradesh Gazette, but no Gazette date is printed (p5). It extends to the whole State of Madhya Pradesh (p5).

The substantive thrust is to align the principal regulations with the PM Surya Ghar Muft Bijli Yojna (PMSG:MBY), defined as a Government of India scheme launched on 29.02.2024 (p5). For prosumers applying for net metering connections under PMSG:MBY, the amendment bars the distribution licensee from charging the processing fee (p6), removes the need for a separate agreement—the agreement is appended to the application and executed online at application (p6)—and bars any meter-testing fee (p6). It also amends cross-references in Regulation 8A(3)(b) and replaces 'group net metering agreement' with 'virtual net metering agreement' in Regulation 8D(4)(d) (p6). Regulation 9 is replaced with a new RPO provision: energy generated by a prosumer under net metering, group net metering, gross metering and virtual net metering counts toward the distribution licensee's RPO, with provisos for renewable generation meters read by the licensee and for unmeasured units to be treated under the 2021 RE regulations (p7). A stray page 3 fragment lists terms under a Renewable Purchase Obligation heading but is not readable as operative text (p3).

Standard name
Net Metering and Rooftop Solar
Primary topics
Net metering, Renewable purchase obligation (RPO / RCO), Connection and miscellaneous charges

Read with this

2 more documents belong here and are not on Voltaic: 2 copies in another language.

Voltaic last read MPERC's website for final documents between 24 Nov 2026 and 26 Nov 2026 (4 pages). A document MPERC issued after the page that lists it was read may not be held by Voltaic yet.