MPERC · Madhya Pradesh Electricity Regulatory Commission
Grid Interactive Renewable Energy Systems and Related Matters Regulations [Revision-II], 2024
Madhya Pradesh Electricity Regulatory Commission (Grid Interactive Renewable Energy Systems and Related Matters) Regulations, [Revision-II], 2024 {RG- 39(II) of 2024}
RegulationDated 14 Mar 2024No.692/MPERC/2024 dated 14th March 2024
1 amendment to it is on Voltaic, dated 18 Jun 2026.
Summary
Summary written by software, from pages 1 to 27 of 34. Check the regulator's original before you rely on it.
The Madhya Pradesh Electricity Regulatory Commission issued this notification (No.692/MPERC/2024, Bhopal, 14 March 2024) to revise and replace its 2022 regulations on grid-interactive renewable energy systems (p1). It is a full principal regulation structured in 16 regulations plus eight annexures; the supplied pages 1–27 cover regulations 1–16 and annexures 1–5.
Regulations 1–2 (p1–4) set the short title, extent to Madhya Pradesh, commencement on Gazette publication, and definitions — including prosumer, parent consumer, participating consumer/beneficiary, RESCO, the four metering arrangements, settlement period and interconnection point.
Regulations 3–5 (p4–6) define scope: four arrangements (net metering, group net metering, gross metering, virtual net metering) and eligibility conditions, including the capacity ceilings that define applicability (net metering up to 500 kW, group net metering and virtual net metering under 100 kW, gross metering up to 1 MW), a 1 kW minimum, limits tied to contract demand/sanctioned load, a bar on open access and third party sale, and a distribution-transformer hosting cap.
Regulation 6 (p6–9) sets the application process — online portal, processing fee, technical feasibility timelines, deemed acceptance for rooftop solar, letter of approval, and compensation for delay. Regulation 7 (p9–10) sets interconnection, anti-islanding and harmonic requirements.
Regulation 8 (p10–17) is the core: separate accounting and settlement rules for each of the four arrangements, covering billing-period credit carry-forward, time-of-day adjustment, settlement-period buy-out rate and annual payout.
Regulations 9–16 (p17–19) cover RPO eligibility of injected energy, metering/AMI requirements, compensation, connection agreements, the Commission's powers to direct, relax and amend, and repeal of the 2022 regulations.
Annexures 1–5 (p19–27) provide the transformer-capacity format and application forms for net metering, gross metering, virtual net metering and group net metering.
Read with this
Amendments and corrections
Other copies of these documents (1)
2 more documents belong here and are not on Voltaic: 2 copies in another language.
Voltaic last read MPERC's website for final documents between 24 Nov 2026 and 26 Nov 2026 (4 pages). A document MPERC issued after the page that lists it was read may not be held by Voltaic yet.
As of its reading of MPERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.