Consumer Grievances Redressal Forum and Ombudsman Regulations, 2013 — First Amendment, 2019

Himachal Pradesh Electricity Regulatory Commission (Consumer Grievances Redressal Forum and Ombudsman) (First Amendment) Regulations, 2019

AmendmentDated 26 Nov 2019HPERC-(H)(1)-1/2012 dated the 26th November, 2019

Amends the Consumer Grievances Redressal Forum and Ombudsman Regulations, 2013.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on hperc.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

The Himachal Pradesh Electricity Regulatory Commission's First Amendment to its Consumer Grievances Redressal Forum and Ombudsman Regulations, 2013, notified at Shimla on 26 November 2019 (p1), reworks the procedural code governing how consumers complain to the Forum and appeal to the Ombudsman. It comes into force on publication in the Himachal Pradesh Rajpatra (p1).

Regulation 2 widens the modes of filing a grievance — in person, post, e-mail, fax or online through the Forum's website — requires a copy for each respondent in addition to three for the Forum, and directs the Forum to decide on merits rather than reject a grievance for want of format (p1–2). Regulation 3 recasts the two priority grievance categories, adding 'safety related issues' alongside non-supply, connection/disconnection/quality/reliability of supply (p2) — a split that then runs through regulation 26 (p2) and Annexure-I's time-line table (p4), and through the grievance-category form in Annexure-II (p4–5).

Costs and remedies change: the Forum must award a minimum cost against a party seeking adjournment, except for a first request (p2); licensees must refund undue charges with simple interest for the period the amount was withheld (p2). Review of Forum orders is restructured, with a new deadline for accepting or rejecting a review application (p2–3), mirrored for the Ombudsman in regulation 37 (p4). Regulation 8 replaces the Ombudsman representation provision and its fee table graded by voltage level (LV, HV, EHV), payable by demand draft or electronic mode (p3); payment of that fee becomes a maintainability condition (p3).

Two provisions narrow the earlier text: the clause treating non-compliance with a Forum order as a regulation breach punishable under section 142 of the Act is omitted (p3), and the Forum must now report 'such details as the Commission may require' when reporting disposal of grievances (p3). Regulation 11 is a pure cross-reference fix (p4).

Standard name
CGRF and Ombudsman
Primary topics
Consumer grievance redressal (CGRF), Electricity ombudsman, Fees payable to the Commission

Read with this

Procedures and orders made under it

Voltaic last read HPERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document HPERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on hperc.org ↗