CGRF and Ombudsman Regulations, 2013 — Fifth Amendment, 2026 — Finalisation Order

In the matter of finalization of the Draft Himachal Pradesh Electricity Regulatory Commission (Consumer Grievances Redressal Forum and Ombudsman) (Fifth Amendment) Regulations, 2026.

OrderDated 13 Oct 2026

Read with the Consumer Grievances Redressal Forum and Ombudsman Regulations, 2013.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on hperc.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the Himachal Pradesh Electricity Regulatory Commission's order finalising the draft Fifth Amendment to its 2013 Consumer Grievances Redressal Forum and Ombudsman Regulations. Announced on 13.10.2026 by the Member-Cum-Chairman, it is a consultation record with reasons rather than a text of amended regulations: it recounts the publication and hearing process, sets out each stakeholder's objections, gives the Commission's response to each, and closes by approving the amendment and directing publication in the Rajpatra (p1, p24).

Pages 1–2 set out the background: the Principal Regulations of 2013, the Commission's finding from CGRF quarterly and annual reports that circle-level Additional Forums receive too few — often no — grievances, and the draft amendment notified on 7 August 2026 and gazetted on 10 August 2026. It documents previous publication under s.181(3): newspaper notices on 13 August 2026, letters to stakeholders on 17 August 2026 with a 14 September 2026 deadline, comments from four stakeholders, and a public hearing on 16.09.2026 (p2–4).

The order's substance lies in two places. On Regulation 5 (p5–7), the Parwanoo Industries Association sought a higher monetary ceiling for the proposed zonal-level Additional Forums and HPSEBL sought to keep four circle-level forums alive; the Commission rejects both and retains the draft, which moves additional forums from circle to zonal level, raises their monetary jurisdiction to Rs. four (4) Lacs and their voltage ceiling to 33 kV, with larger claims going to the headquarters forum. On Regulation 7(1)(ii)(a) (p8–11), the Commission retains the draft raising the required service experience for a Forum's Independent Member from 10 to 20 years, and refuses a lifetime bar on former licensee employees, pointing to appeal to the Ombudsman as the safeguard against bias.

A long final section (p11–24) records objections to Regulations 6, 17, 23–26, 28, 30, 32 and 33 — mobile camps, admission hearings, interim protection, appeal limitation, Ombudsman eligibility, filing fees and appeal deposits — and to rule 15 of the Electricity (Rights of Consumers) Rules, 2020. The Commission declines them all as outside the scope of this amendment, leaving stakeholders free to propose them separately.

Standard name
CGRF and Ombudsman
Primary topics
Consumer grievance redressal (CGRF)

Read with this

Procedures and orders made under it

Voltaic last read HPERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document HPERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on hperc.org ↗