HPERC · Himachal Pradesh Electricity Regulatory Commission
Green Energy Open Access and Banking Regulations, 2024
the Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Green Energy Open Access and Banking) Regulations, 2024
RegulationDated 17 Dec 2024No. HPERC/ED(T)/D(TE)/GEOA/38 dated 17.12.2024
Summary
Summary written by software. Check the regulator's original before you rely on it.
These are HPERC's framework regulations for green energy open access (GEOA) and banking in Himachal Pradesh, notified on 17 December 2024 under s.181 read with ss.39, 40, 42, 61 and 86 of the Electricity Act 2003, and framed to give effect to the Electricity (Promoting Renewable Energy through Green Energy Open Access) Rules, 2022 (p1). Commencement is deferred: they take effect on a date the Commission is yet to notify (p1).
Regulations 1–2 (p1–3) state the title, extent to the whole State and application to connectivity and open access for green energy — including non-fossil waste-to-energy — over the intra-State transmission and distribution systems, and define the working vocabulary: green energy, banking, the GOAR portal, obligated entity, standby charges, 'entity'/GEOA consumer and the existing-consumer category. As printed, the definitions begin at clause (b) (p1).
Regulation 3 (p3) splits nodal-agency duties — HPSLDC for short-term GEOA, HPPTCL (the STU) for medium- and long-term — and requires them to publish GEOA information on the Central Nodal Agency's portal. Regulation 4 (p4) classifies consumers by duration of system use into long-, medium- and short-term. Regulations 5–6 (p4–5) set eligibility (a 100 kW contracted demand or sanctioned load threshold for non-captive consumers; no load limit for captive), let consumers requisition green supply from their DISCOM, count surplus green purchase towards RPO, and preserve existing GEOA agreements.
Regulations 7–9 (p5–6) give the criteria for allowing open access, a curtailment priority order (non-green short-term curtailed first, DISCOM last, pro-rata within a category), and the application route: registration on the central GOAR portal, Central Nodal Agency formats, first-in-first-out processing, and deemed approval if the State Nodal Agency does not decide in time. Regulation 10 (p6) covers metering and real-time communication to SLDC.
Regulation 11 (p6–9) is the commercial core. It enumerates the charge heads the Commission will determine — transmission, wheeling, cross-subsidy surcharge, additional surcharge, standby, banking and other fees — then specifies how each applies, including wheeling-loss treatment for banked energy, exemptions and escalation caps on cross-subsidy and additional surcharge, standby supply priced by reference to normal tariff with a notice-based escape, and the banking mechanism: monthly banking, a permitted quantum tied to the consumer's direct DISCOM consumption, TOD-linked drawal, lapse of unused credit at cycle end with RECs issued for lapsed energy, an in-kind banking charge, and a direction to frame a banking procedure and model banking agreement.
Regulations 12–15 (p10) provide for green certificates from the DISCOM, collection and disbursement of charges through the nodal agencies, dispute resolution and hearing before refusal, and SLDC web reporting. Regulations 16–20 (p10–11) give the Commission powers to issue directions, relax provisions, remove difficulties and amend, with a savings clause.
Read with this
Commencement notices and reasons
Earlier drafts
Voltaic last read HPERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document HPERC issued after the page that lists it was read may not be held by Voltaic yet.
As of its reading of HPERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.