RERC · Rajasthan Electricity Regulatory Commission
Terms and Conditions for Tariff determination from Renewable Energy Sources (Second Amendment) Regulations, 2023
Rajasthan Electricity Regulatory Commission (Terms and Conditions for Tariff determination from Renewable Energy Sources) (Second Amendment) Regulations, 2023
AmendmentDated 8 Dec 2023No. RERC/Secy./Reg./153 dated December 8, 2023
Amends the Terms and Conditions for Tariff Determination from Renewable Energy Sources Regulations, 2020.
Summary
Summary written by software. Check the regulator's original before you rely on it.
A short, ten-clause amendment to RERC's 2020 renewable energy tariff regulations, notified at Jaipur on 8 December 2023 under notification No. RERC/Secy./Reg./153 (p5). It does not restate tariffs; it resets the temporal boundaries, the bidding-versus-adoption routes and the legacy-plant carve-outs of the principal Regulations, which is why anyone pricing or procuring RE capacity in Rajasthan needs it.
Amendments 1–4 deal with scope and commencement: the Regulations extend to the whole of Rajasthan and apply to tariff determination from 1 April 2020 up to 31 March 2026 (p5); Reg. 3.2 requires the Commission to adopt tariffs set through a transparent bidding process under Central Government s.63 guidelines, or — where no central guidelines exist — under bidding guidelines approved by the Commission (p5); and Reg. 5.1 fixes the Control Period at six financial years from 1 April 2020 to 31 March 2026 (p5).
Amendments 5–8 deal with procurement and legacy plants. A new proviso to Reg. 7.2 directs distribution licensees to run competitive bidding for technologies for which the Central Government has issued no bidding guidelines — naming biomass, biomass gasifier and biogas projects — with a carve-out for plants already commissioned or whose PPAs the Commission approved before notification (p6). Reg. 8.1 preserves generic tariffs for such plants; Reg. 43.1 splits biomass fuel cost between legacy/earlier-control-period plants and plants to be commissioned through competitive bidding (p6); and Reg. 44.2 allows solar power usage only in projects commissioned by 31.03.2026 (p6).
Amendments 9–10 cover holdover and post-PPA pricing and banking. Reg. 88 keeps the 2023-24 tariff in force for 2024-25 and 2025-26 while energy is supplied under the PPA, adds annual variable-charge escalation with 2023-24 as base year, and sets a reduced extended-period tariff once the PPA term ends (p6–7). New Reg. 93.6A keeps the banking provisions alive until 31.03.2030 for existing projects and those commissioned up to 31.03.2026 (p7).
Read with this
The regulation
Amendments and corrections
Voltaic last read RERC's website for final documents on 24 Nov 2026. A document RERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.