Skip to content

RERC · Rajasthan Electricity Regulatory Commission

Terms and Conditions for Determination of Tariff (Second Amendment) Regulations, 2023

Rajasthan Electricity Regulatory Commission (Terms and Conditions for Determination of Tariff) (Second Amendment) Regulations, 2023

AmendmentDated 27 Jan 2023No. RERC/Secy./Reg. No. 146 dated January 27, 2023

Replaced by Terms and Conditions for Determination of Tariff Regulations, 2025

See that regulation for the date it took effect and for anything it keeps in force.

Amends the Rajasthan Tariff Regulations, 2019.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on rerc.rajasthan.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a two-clause amendment by the Rajasthan Electricity Regulatory Commission to its principal tariff-determination regulations, notified at Jaipur on 27 January 2023 as No. RERC/Secy./Reg. No. 146 (p2). It comes into force from the date of publication in the official gazette; the gazette date itself is not printed (p2).

Clause 2 inserts a new sub-regulation (3) into regulation 58: all new intra-State transmission projects costing Rupees Two Hundred fifty Crore or more must be developed through Tariff Based Competitive Bidding, following Central Government guidelines issued under section 63 of the Electricity Act (p2–3). A proviso requires the transmission system, including all connected upstream and downstream systems, to be treated as a single project when inviting bids, and makes the threshold applicable to every intra-State transmission project whose approval is still pending with the Commission (p3).

Clause 3 substitutes regulation 78(1), directing the distribution licensee to procure electricity in accordance with the National Tariff Policy and the Commission's regulations, and to submit cost estimates for power procurement together with the annual procurement plan required under Regulation 77 (p3).

The document carries no schedules, formats or definitions.

Standard name
Tariff Regulations
Primary topics
Competitive bidding, Power procurement and PPAs

Read with this

Voltaic last read RERC's website for final documents on 24 Nov 2026. A document RERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on rerc.rajasthan.gov.in ↗

Report an issue with this document