RERC · Rajasthan Electricity Regulatory Commission

Terms and Conditions for Determination of Tariff (First Amendment) Regulations, 2020

Rajasthan Electricity Regulatory Commission (Terms and Conditions for Determination of Tariff) (First Amendment) Regulations, 2020

AmendmentDated 28 Feb 2020Published in the Gazette 12 Mar 2020No. RERC/Secy./Reg. No. 136 dated February 28, 2020

Replaced by Terms and Conditions for Determination of Tariff Regulations, 2025

See that regulation for the date it took effect and for anything it keeps in force.

Amends the Rajasthan Tariff Regulations, 2019.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on rerc.rajasthan.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a short amending instrument issued by the Rajasthan Electricity Regulatory Commission. The Rajasthan Gazette Extraordinary of 12 March 2020 (p1) carries a Commission notification dated Jaipur, 28 February 2020 (p2), numbered RERC/Secy./Reg. No. 136 and made under section 61 read with section 181 of the Electricity Act, 2003 (p2). The First Amendment Regulations come into force from the date of publication in the official gazette (p3).

The operative content is six substitution clauses. Clause 2 rewrites regulation 5(4) to give a licensee or the SLDC the option, when filing an ARR/tariff petition for any year of the Control Period, to instead file a petition for Multi Year Tariff determination for the remaining period of that Control Period; an opting-in licensee must forecast ARR, expected revenue from existing tariffs and proposed tariff for each remaining year, and the Commission determines ARR and tariff for each such year. Three provisos attach: a true-up petition for the previous year must be filed each year, with a re-determination petition permitted; the Managing Director of the opting company is responsible for timely filing of true-up petitions, and failure to file within the specified time strips the entitlement to charge the increased tariff and exposes the licensee/SLDC to penalty as the Commission may determine; and excess earnings are adjusted in the next true-up, with the Commission empowered to issue a suo-motu order revising tariff where there are excessive profits or true-up petitions are not filed (p3).

Clauses 3–6 make the consequential changes that make the MYT option coherent: regulation 6(1)'s third proviso requires an MYT petition covering ARR approval and tariff determination for each remaining year; regulation 10(1)'s first proviso requires the Commission to determine ARR and tariff for each financial year for which a petition is filed as part of the MYT approval; and regulations 61(2) and 73(2) require the transmission licensee/SLDC and the distribution licensee respectively to submit a capital investment plan for each remaining year of the Control Period (p3–4). The Secretary signs by order of the Commission (p4).

Standard name
Tariff Regulations
Primary topics
Tariff determination, Multi Year Tariff (MYT), ARR and true-up

Read with this

Voltaic last read RERC's website for final documents on 24 Nov 2026. A document RERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on rerc.rajasthan.gov.in ↗

Report an issue with this document