KERC · Karnataka Electricity Regulatory Commission
Implementation of Solar Rooftop Photovoltaic Power Plants Regulations, 2016
KERC (Implementation of Solar Rooftop Photovoltaic Power Plants) Regulations, 2016
RegulationDated 15 Dec 2016Published in the Gazette 19 Dec 2016No.S/03/1 dated 15th December, 2016
Replaced by Grid Interactive Distributed Solar Photovoltaic (DSPV) Plants Regulations, 2026
See that regulation for the date it took effect and for anything it keeps in force.
Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or purported to have been done under the repealed Regulations shall be deemed to have been done or purported to have been done under these Regulations.”
Summary
Summary written by software. Check the regulator's original before you rely on it.
The Karnataka Electricity Regulatory Commission makes a self-contained framework for grid-connected solar rooftop photovoltaic (SRTPV) plants on consumers' premises (p1). It applies to distribution licensees and to 'eligible consumers' in Karnataka (p2), and it took effect from gazette publication on 19 December 2016, following a draft notified on 2 September 2016 and a public hearing on 23 November 2016 (p1–2).
Regulations 1–3 set commencement, the definitional vocabulary (gross metering, net metering, interconnection point, SRTPV plant, REC, eligible consumer) and the general principle that licensees must offer gross or net metering on a non-discriminatory, first-come-first-served basis (p2–3). Regulation 4 fixes who may install and how large: capacity of not less than one kilowatt but not exceeding one megawatt, capped further by sanctioned load and by a State-wide capacity ceiling the Commission approves (p3). Regulation 5 lays out the implementation pipeline — licensee approval within a set number of days of application, PPA signing, a commissioning deadline with a tariff consequence if missed, and quarterly licensee reporting (p3).
Regulation 6 is the technical core: voltage-level connectivity by installed capacity, transformer and line loading limits, cost of network up to the interconnection point, harmonics, and a full safety regime — anti-islanding, automatic synchronisation, protective functions, isolating switch, and the licensee's right to disconnect (p3–5). Regulation 7 covers how generic tariffs are filed and determined and how long a signed PPA tariff holds (p5). Regulation 8 sets the cost-of-service building blocks the Commission uses to build that generic tariff — CUF, single-part tariff structure, tariff period and levelisation, capital cost scope, debt-equity, loan and finance charges, depreciation, return on equity, working capital, O&M escalation and income tax treatment (p6–7).
Regulations 9–11 deal with metering (bi-directional meters, replacement cost, testing and sealing), energy accounting and billing settlement under gross and net metering, and the PPA approval pathway — deemed approval for smaller plants, express Commission approval above a capacity threshold with a fee (p7–9). Regulation 12 addresses sharing of CDM carbon-credit proceeds and confirms that rooftop purchases count toward the licensees' solar RPO, with carve-outs for government-funded installations on government buildings. Regulation 13 gives the Commission powers to issue directions, relax provisions after hearing, and amend or repeal the regulations (p9).
Read with this
Proposed changes (drafts with no final yet)
Voltaic last read KERC's website for final documents on 24 Nov 2026 (3 pages) and for drafts on 23 Nov 2026. A document KERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.