Rajasthan Electricity Grid Code, 2008

Rajasthan Electricity Regulatory Commission (Rajasthan Electricity Grid Code) Regulations 2008

CodeDated 24 May 2008No. RERC / Secy / Reg - 74 dated 24.05. 2008

Replaced by Rajasthan Electricity Grid Code, 2024

See that regulation for the date it took effect and for anything it keeps in force.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done, or any action taken or purported to have been done or taken including any procedure, minutes, reports, confirmation or declaration of any instrument executed under the repealed regulations shall be deemed to have been done or taken under the relevant provisions of these regulations.”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on rerc.rajasthan.gov.in ↗

Summary

Summary written by software, from pages 1 to 19 of 34. Check the regulator's original before you rely on it.

REGC 2008 is the Rajasthan Electricity Regulatory Commission's principal grid code, notified at Jaipur on 24 May 2008 as No. RERC/Secy/Reg-74 (p1). Made under s.181 read with s.86(1)(h) of the Electricity Act 2003, it supersedes Part-1 of the earlier grid code published by RVPN and takes effect from the date of gazette publication, which is not printed (p1). It binds Users at 33kV and above — transmission licensees, state generating stations including IPPs, renewable energy plants, generating/transmission companies connected to the State Transmission System, discoms with HV/EHV consumers directly connected to it, open access customers and traders (p1). Chapters I–III carry the title, applicability, objectives, scope and the full definition set (p1–6).

Chapter IV builds the governance machinery: a State Power Committee chaired by the STU with defined membership, quorum, meeting cycle and amendment route; three functional committees (Technical, Commercial, Protection Coordination); and non-compliance, penalty and derogation provisions (p6–9).

Chapter V sets who plans the transmission system, on what data, forecasts and security criteria (p10–12). Chapter VI sets connection conditions — safety isolation, site responsibility schedules, connection points by user class, and system performance standards for frequency, voltage, harmonics and imbalance (p12–16). Chapter VII sets system security obligations on governors, AVRs, disturbance recorders and under-frequency load shedding (p16–18). Chapter VIII sets the annual and in-year outage planning cycle and SLDC's power to defer outages (p18–19).

Chapter IX, operational planning, begins at p19. Chapters X–XVI — scheduling/despatch/accounting, frequency-voltage-loading management, contingency planning, inter-user boundary safety, incident and accident reporting, protection, and data registration — appear only in the contents list (p1).

Standard name
Grid Code
Primary topics
Grid operation and grid code, Technical standards, Connectivity and GNA

Read with this

Amendments and corrections

Voltaic last read RERC's website for final documents on 24 Nov 2026. A document RERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on rerc.rajasthan.gov.in ↗