Grid Interactive Solar Rooftop Photovoltaic Systems under Net/Gross Metering Regulation, 2023 — Consolidated (First Amendment, 2025; Errata, 2026)

Andhra Pradesh State Electricity Regulatory Commission (The Grid Interactive Solar Rooftop Photovoltaic Systems under Net/Gross Metering ) Regulation, 2023.

Consolidated copyDated 31 Dec 2025REGULATION NO. 4 OF 2023 dated 22.02.2024

A consolidated copy of the Regulation 4 of 2023, published by APERC for reference. It may not include the latest amendments; read it with the amendments listed for the regulation.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on aperc.gov.in ↗

Summary

Summary written by software, from pages 1 to 41 of 62. Check the regulator's original before you rely on it.

This is APERC Regulation No. 4 of 2023 — the Grid Interactive Solar Rooftop Photovoltaic System under Gross/Net Metering Regulation, 2023 — presented as a consolidated text with the First Amendment (Regulation No. 10 of 2025, dated 08-12-2025) and an Errata dated 19-01-2026 (p1). It replaces earlier APERC-approved SRTPVS guidelines for new cases and creates a framework for consumers and DISCOMs in Andhra Pradesh to install grid-connected rooftop solar with or without battery storage (p1–3). It comes into force on Gazette publication, but no Gazette date is printed; the regulation itself is dated 22.02.2024 (p3, p23).

The operative regulation (pp3–23) defines prosumers and the available metering options — individual net metering, group net metering, virtual net metering, gross metering and net billing/net feed-in (pp3–8). It sets eligibility for all AP DISCOM consumers, capacity bands by metering type and voltage level, limits on cumulative SRTPVS capacity at distribution transformers and feeders, and DISCOM disclosure duties (pp8–12). It specifies interconnection with CEA and APERC grid standards, metering responsibilities and costs, and a feed-in tariff that applies for 25 years or project life (pp12–14). It governs wheeling/T&D charges and cross-subsidy surcharge treatment, MNRE subsidies, application and technical feasibility procedures and timelines, agreement and commissioning timelines, energy settlement and billing (including ToD and group/virtual netting), and DISCOM capacity targets (pp14–22). It also contains power to relax, issue practice directions, remove difficulties, amend, and a repeal-and-savings clause that protects existing projects and agreements (pp22–23).

The annexures (pp24–41) provide the application format, declarations, deficiency and feasibility formats, and the individual and group/society net-metering/gross-metering agreements.

Standard name
Net Metering and Rooftop Solar
Primary topics
Net metering, Gross metering, Net billing

Read with this

Voltaic last read APERC's website for final documents on 24 Nov 2026 (2 pages) and for drafts on 21 Nov 2026. A document APERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on aperc.gov.in ↗