AERC · Assam Electricity Regulatory Commission
Multi Year Tariff Regulations, 2015 — Generation, Transmission, SLDC, Wheeling and Retail Supply
Assam Electricity Regulatory Commission (Terms and Conditions for determination of Multi Year Tariff) Regulations, 2015 for Generation, Transmission, SLDC, Wheeling and Retail Supply
RegulationDated 2 Jun 2015No. AERC. 396/2012/Pt-II/13 dated The 2nd June, 2015
Replaced by MYT Regulations, 2018 for Generation, Transmission, SLDC, Wheeling and Retail Supply
See that regulation for the date it took effect and for anything it keeps in force.
Summary
Summary written by software, from pages 1 to 22 of 90. Check the regulator's original before you rely on it.
This is the Assam Electricity Regulatory Commission (Terms and Conditions for determination of Multi Year Tariff) Regulations, 2015, notified on 2 June 2015 (p1). The regulations replace the 2006 tariff regulations, come into force on Gazette notification, extend to Assam, and apply for tariff determination from 1 April 2016; the 2006 regulations continue to govern the period up to FY 2015-16 including review matters (p1). They bind existing and future generating companies, transmission licensees, distribution licensees and SLDC under s.62, but do not apply to renewable energy generation, which remains under the 2012 RE tariff regulations; competitively bid tariffs under s.63 are adopted (pp1–2).
Chapter 1 (pp1–10) covers short title, extent, applicability and commencement, then definitions—including accounting and allocation statements, availability, change in law, control period, declared capacity, COD, force majeure, infirm power, NAPAF, PLF and useful life.
Chapter 2 (pp11–20) sets the object and scope and the MYT framework: a first control period of 1 April 2016 to 31 March 2019, with later five-year blocks or as the Commission decides (pp11–12). It requires business plans and capital investment plans, with segment-specific contents and a 60-day approval timeline (pp13–15); forecasts for power purchase and ARR, with EE/DSM targets and trajectories for specified variables (pp15–17); annual performance review and true-up, including filing at least 120 days before the close of each year (p17); categorization of ARR items as controllable or uncontrollable (pp18–20); pass-through of uncontrollable items; and one-third sharing of controllable gains/losses (p20). Carrying cost on trued-up amounts is SBI base rate plus 350 basis points (p18). Fuel and power purchase price variations go to the separate 2010 formula regulations (p20). The Commission may act suo motu (pp20–21).
Chapter 3 (pp21–22) starts the procedure: application forms, fees under the 2009 Fees Regulations, proceedings under the 2004 Conduct of Business Regulations, end-of-control-period review, and initial rules for generation tariff—existing stations with approved PPAs, new stations under approved PPAs, and transfer price for own generation. Chapters 4–10 are referred to (PPA approval, own-generation transfer pricing, and substantive tariff terms for generation, transmission, distribution wheeling, retail supply and SLDC).
Read with this
Amendments and corrections
- Dated 1 Sep 2015Multi Year Tariff Regulations, 2015 — Addendum (Appendices I and II)
- Dated 8 Nov 2017MYT Regulations, 2015 — First Amendment, 2017