This is HPERC's principal regulation creating a Resource Adequacy (RA) framework for Himachal Pradesh, notified on 28 April 2025 and taking effect on the date of Gazette publication (p1). It binds the State's distribution licensees as the primary planning entity, with defined roles for the SLDC, STU, generating companies and other grid-connected entities (p1).
Regulations 1–3 set commencement, extent, application, the objective and the defined vocabulary — capacity credit, net load, EENS, NENS, LOLP, planning reserve margin and the three planning horizons: short (one year), medium (five years) and long term (ten years), all on a financial-year basis (p1–4).
Chapter 2 (Reg 4) describes the framework as a four-step cycle — demand assessment and forecasting, generation resource planning, procurement planning, and monitoring and compliance — run on a ten-year annual rolling basis (p4–5). Chapter 3 (Regs 5–6) specifies how licensees build long/medium-term forecasts by consumer category using CEA forecast guidelines and named modelling methods, how they adjust for DSM, open access, EVs, ToD tariffs, agricultural and seasonal factors, how peak demand is derived from energy forecasts, scenario analysis, hourly short-term forecasting, and how SLDC aggregates and escalates State demand forecasts (p5–10).
Chapter 4 (Regs 7–10) is the core: it sets out generation resource planning steps, a net-load-based methodology for computing capacity credits for RE, hydro and thermal resources, the assessment of planning reserve margin against reliability indices, and how licencees compute their resource gap, prepare LT/MT/ST-DRAPs, and reconcile them with CEA's LT-NRAP and NLDC's ST-NRAP, including contract-tenure mix, tie-up demonstration and submission to CEA and the Commission (p10–18).
Chapter 5 (Regs 11–16) governs procurement: least-cost optimal resource mix, contracting route and tenure, capacity sharing, prior Commission approval for PPAs/PSAs, and the exemption cases in which additional short-term procurement may proceed without prior approval (p18–23). Chapter 6 (Reg 17) makes compliance mandatory with non-compliance charges possible; Chapter 7 (Regs 18–19) prescribes the data-sharing protocol and the annual calendar of submissions; Chapter 8 (Regs 20–26) covers merit order publication, consultation, and the Commission's powers to issue directions, relax, remove difficulties, amend, plus a transitional provision preserving the Commission's inherent procedural powers (p23–27). Annexure-I sets out the optimisation constraints the licensee must model — reserve margin, portfolio balance, RE and conventional generation, RPO, storage, spinning reserve and demand response (p28–30).
Read with this
Commencement notices and reasons
- Dated 28 Apr 2025Resource Adequacy Framework Regulations, 2025 — Finalisation Order
Earlier drafts
- Dated 27 Feb 2025Framework for Resource Adequacy Regulations, 2025 — Draft
Voltaic last read HPERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document HPERC issued after the page that lists it was read may not be held by Voltaic yet.
As of its reading of HPERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.