Power System Development Fund Regulations, 2010 — Statement of Reasons
Statement of Reasons
Statement of reasonsDated 1 Jun 2010No.L-7/14/2010/CERC dated 1.6.2010
Replaced by Power System Development Fund Regulations, 2014
See that regulation for the date it took effect and for anything it keeps in force.
The commission's reasons for the Power System Development Fund Regulations, 2010.
Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or any action taken or purported to have been done or taken including any procedure, minutes, annual reports, confirmation or declaration or any instrument executed under the repealed regulations shall be deemed to have been done or taken under the relevant provisions of these regulations.”
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is the Statement of Reasons (SoR) issued with the Central Electricity Regulatory Commission (Power System Development Fund) Regulations, 2010 — it is not the regulations themselves.
Pages 1–2 explain why a single fund was thought necessary: surpluses sitting in three grid-related regulatory accounts — the Unscheduled Interchange Pool Account Fund, the Congestion Charge Account and the Reactive Energy Charges Account — were being kept in RLDC books although the Commission treats them as regulatory funds. Separate regulations were wanted to hold them independently, keep proper books, process applications for sanction of grants to schemes, track funded projects and seek income-tax exemption.
Pages 3–4 set out the gist of stakeholder comments on the draft, including a challenge to CERC's competence to frame the regulations, arguments that the fund conflicts with sections 61, 62 and 69, the sub judice status of the UI regulations, and practical suggestions on region-wise accounts, use of congestion charges, defining 'strategic importance', incentives to reactive-energy suppliers, website disclosure of proposals and the composition of the Managing Committee.
Pages 4–10 record the Commission's reasoning and decisions on each point. It rejects the competence and tariff objections, relying on Supreme Court authority on the width of the power to regulate and on UI charges as settlement rates for deviation rather than tariff; accepts renaming 'RLDC reactive energy charges' to 'Reactive energy charges' in three provisions; decides that separate accounts be kept for each head of regulatory charge, region-wise where the parent regulation requires it; that no tariff be allowed on assets created out of the Fund; that proposals received and release priorities be hosted on the Commission's website; that the Managing Committee be reconstituted away from Commission members towards NLDC/RLDC/RPC representation; and that Fund balances may be invested under the Indian Trusts Act, 1882 or under guidelines approved by the Commission. Paragraph 3.17 directs the regulations to be finalised, gazette-published and effective from publication; the gazette date is not printed here.
Read with this
The regulation
- Dated 4 Jun 2010Power System Development Fund Regulations, 2010
Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.