Skip to content

CERC · Central Electricity Regulatory Commission

Power System Development Fund Regulations, 2014

Central Electricity Regulatory Commission (Power System Development Fund) Regulations, 2014

RegulationDated 9 Jun 2014No. L-1/148 /2014/CERC dated 9 June, 2014

Replaced by Power System Development Fund Regulations, 2019

See that regulation for the date it took effect and for anything it keeps in force.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or any action taken or purported to have been done or taken including any procedure, minutes, annual reports, confirmation or declaration or any instrument executed under the repealed regulations shall be deemed to have been done or taken under the relevant provisions of these regulations.”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the CERC notification of 9 June 2014 making the Central Electricity Regulatory Commission (Power System Development Fund) Regulations, 2014, a self-contained framework for a dedicated fund that pays for grid-strengthening works (p1). Regulations 1 and 2 give the short title and commencement and define the vocabulary the rest of the instrument runs on — PSDF, Congestion Amount, Congestion Charge, Deviation Settlement Charges, Reactive Energy Charges, the Detailed Procedure, and the two committees (p1–2).

Regulation 3 constitutes the Power System Development Fund and specifies which residual streams feed it: congestion charges and congestion amounts left after settlement, deviation settlement charges, reactive energy charges and additional transmission charges from STOA explicit auctions, plus any further charges the Commission notifies later; it also requires monthly transfer by collecting agencies and operation through the Public Account of India (p3). Regulation 4 states the purposes the fund may finance — strategic transmission, reactive compensation, protection schemes and audits, R&M, and related studies or PMUs — extends this to distribution utility projects incidental to the ISTS, excludes private sector projects, and sets the prioritisation criteria (p4).

Regulation 5 names NLDC as Nodal Agency and lists its secretariat, procedure, budget, audit and reporting functions (p4–5). Regulations 6 and 7 create the Appraisal Committee (chaired by CEA) and the inter-ministerial Monitoring Committee (chaired by Secretary, Power), the latter sanctioning projects and supervising implementation (p5–6). Regulation 8 lays out the application-to-sanction chain: sponsoring entities submit to the Nodal Agency, appraisal, Commission confirmation that projects fit the regulations and are prioritised, then Monitoring Committee sanction (p6). Regulations 9 to 13 cover the grant pattern, execution and O&M obligations, budget and audit through the Detailed Procedure, implementing agencies and outcome-based monitoring, and the Annual Report to Government and Parliament (p7). Regulations 14 and 15 give the Commission power to remove difficulties and repeal the 2010 PSDF Regulations with a savings clause (p8).

Primary topics
Power System Development Fund (PSDF)

Read with this

Amendments and corrections

Commencement notices and reasons

Other copies of these documents (2)

Earlier drafts

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cercind.gov.in ↗

Report an issue with this document