RERC · Rajasthan Electricity Regulatory Commission
Tariff for Renewable Energy Sources (Biomass, Biogas and Biomass Gasifier Energy) Regulations, 2015 — First Amendment, 2019
Rajasthan Electricity Regulatory Commission (Terms and Conditions for Determination of Tariff for Renewable Energy Sources- Biomass, Biogas and Biomass Gasifier Energy) (First Amendment) Regulations, 2019
AmendmentDated 5 Mar 2019No.RERC/Secy./Regulation - 129 dated 05 March, 2019
Replaced by Terms and Conditions for Tariff Determination from Renewable Energy Sources Regulations, 2020
See that regulation for the date it took effect and for anything it keeps in force.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is a 12-page amendment by the Rajasthan Electricity Regulatory Commission to its 2015 tariff regulations for biomass, biogas and biomass-gasifier based power plants. It was issued at Jaipur on 5 March 2019 under notification number RERC/Secy./Regulation - 129 and takes effect from gazette notification (p1).
The opening clauses stretch the Principal Regulations' control period by one year: the earlier end point of FY 2018-19 (31 March 2019) becomes FY 2019-20 (31 March 2020), and the four-year figure used in the control-period/useful-life provisions becomes five (p1). The same one-year shift also appears in a capital-cost clause (p1) and in the fuel-mix clause, which now runs till 31.03.2020 (p5).
The middle of the document builds out a new project-specific tariff track. A new Regulation 6A lets the Commission determine project-specific tariffs case by case for biomass gasifier, biogas, MSW/RDF with Rankine cycle, hybrid and MNRE-approved technologies and government-scheme projects, and expressly allows it to deviate from the financial and technical norms in Parts III–VI for recorded reasons (p2). A new sub-regulation sets out what a project-specific tariff petition must contain — forms, detailed project report, subsidy and incentive statements, and any further information the Commission requires (p2–3). Amendments to Regulations 9, 11, 12, 13, 14, 15 and 16 then align capital-cost break-up, debt-equity treatment, loan tenure, interest-rate benchmarks, depreciation, return on equity and working-capital interest with these two tariff tracks (p3–5).
Later clauses freeze FY 2017-18 capital costs for the remaining control period in the various technology chapters (p5–6), link biogas prices to changes in biomass fuel price (p6), route REC-mechanism projects to the RERC REC and RPO Compliance Framework Regulations, 2010 (p6), and rewrite energy accounting and banking, including set-off of excess injected energy and the treatment of unutilized banked energy (p7). The closing five pages are the petition forms: Form 1.1 for biomass power assumptions and Form 1.2 for year-wise tariff components (p8–12).