Standards of Performance of inter-State transmission licensees Regulations, 2012

Central Electricity Regulatory Commission (Standards of Performance of inter-State transmission licensees) Regulations, 2012

Regulation · Gazette copyDated 17 Sep 2012Published in the Gazette 21 Sep 2012No. L-1/67/2012-CERC. dated New Delhi, the 17th September, 2012

The Gazette copy of the Standards of Performance of inter-State Transmission Licensees Regulations, 2012.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

The Central Electricity Regulatory Commission (Standards of Performance of inter-State transmission licensees) Regulations, 2012 were notified on 17 September 2012 and published in the Gazette of India on 21 September 2012, from which date they come into force (p1, p9). They apply to every inter-State transmission licensee, including deemed licensees (p9–10).

Chapter 1 (p9–10) sets the short title, commencement, scope and definitions — the Act, the Commission, the inter-State transmission system, the licensee, the "user" (generators, STUs, SEBs, load-serving entities and bulk consumers connected to the ISTS) and the "affected person" who may claim compensation.

Chapter 2 (p10–12) is the operative core. Regulation 5 makes compliance mandatory and prescribes two standards: element-wise monthly transmission system availability, computed on the basis of the CERC (Terms and Conditions of Tariff) Regulations, 2009, with a minimum availability floor for each element class; and maximum restoration times after defined failure types (insulator failure, tower collapse with or without ERS, conductor snapping, earth wire, ICT and reactor failures), differentiated by terrain. Availability is to be certified by the Member Secretary of the Regional Power Committee. Regulation 6 makes non-adherence a ground for compensation without prejudice to penalty; Regulation 7 sets the procedure — application to the Commission, a hearing, compensation capped at the transmission charges of the affected element, no recovery of that compensation through tariff, and a 90-day limitation period.

Chapter 3 (p12–13) requires licensees to report achieved performance, compensation cases and amounts to the Commission half-yearly (by 31 October and 30 April) in the Schedule formats, and to publish monthly performance and compensation on their websites.

Chapter 4 (p13) gives the Commission power to relax standards during force-majeure events and to remove difficulties in giving effect to the Regulations.

The Schedule (p14–16) supplies the reporting formats: outage details, restoration-time exceedances, compensation paid, system-protection indices (dependability, security, reliability) to be compiled by POSOCO, and detailed restoration-time data by element and terrain.

Standard name
Standards of Performance
Primary topics
Standards of performance, Transmission availability and outages

Read with this

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.