Rooftop Solar Grid Interactive Systems Based on Net Metering/Gross Metering Regulations, 2021

The Haryana Electricity Regulatory Commission (Rooftop Solar Grid Interactive Systems Based on Net Metering/Gross Metering), Regulations, 2021.

RegulationDated 19 Jul 2021Regulation No. HERC/54/2021 dated The 19th July, 2021

2 amendments to it are on Voltaic, the latest dated 30 Oct 2025.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on herc.org.in ↗

Summary

Summary written by software, from pages 1 to 40 of 53. Check the regulator's original before you rely on it.

The Haryana Electricity Regulatory Commission issued these principal regulations on 19 July 2021 (Regulation No. HERC/54/2021) under ss. 61, 66, 86(1)(e) and 181 of the Electricity Act, 2003, to govern grid-connected rooftop solar systems in Haryana under net metering or gross metering (p1). They extend to the whole State and come into force from the date of Gazette publication.

Chapter I defines the framework's vocabulary—eligible consumer, prosumer, net/gross metering, net/solar/gross meters, interconnection point, settlement period, third-party owner and related terms (p1–5). Chapter II sets scope: distribution licensees and their consumers/prosumers, excluding agricultural tube-well (AP) consumers; it allows self-owned or third-party/RESCO systems, bars net metering for open-access consumers, and applies capacity caps at consumer, transformer and state-wide levels (p5–9). Chapter III requires each DISCOM to create an in-house rooftop solar monitoring mechanism, with constitution, functions and quarterly reporting detailed in Annexure A (p9–10, 25–26).

Chapter IV covers interconnection: voltage level, CEA technical/safety standards, islanding protection, earthing, synchronization, harmonic limits, disconnection rights and the split of operation/maintenance responsibility at the meter (p10–12); it also addresses third-party-owned systems (p12–13). Chapter V is the operational core: metering requirements and AMR/telemetry thresholds (p13–14); net metering energy accounting, including cumulative caps, billing-cycle carry-forward, settlement-period lapsing of credits and treatment of kVAh, fixed/demand charges and MMC (p14–16); gross metering accounting and Solar Injection Compensation, including a five-year fixed tariff (p16–18); exemptions from wheeling, cross-subsidy, transmission/distribution, banking and additional surcharges (p18); and meter-defect accounting (p18–19).

Chapter VI lays out the application process—filing, fee, acknowledgement, technical feasibility, letter of approval, installation and agreement timelines, meter procurement, work completion, commissioning and subsidy/CFA process (p19–22), supported by standard formats at pp27–40. Chapter VII provides that non-obligated consumers' rooftop solar consumption counts toward DISCOM RPOs (p23). Chapter VIII gives the Commission powers to issue directions, remove difficulties, relax and amend, and repeals the 2019 net metering regulations while saving existing arrangements (p23–24).

Standard name
Net Metering and Rooftop Solar
Primary topics
Net metering, Gross metering, Energy accounting and settlement

Read with this

Voltaic last read HERC's website for final documents on 24 Nov 2026 (2 pages). A document HERC issued after the page that lists it was read may not be held by Voltaic yet.

As of its reading of HERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on herc.org.in ↗