Skip to content

BERC · Bihar Electricity Regulatory Commission

Prayas (Energy Group) Submission on Draft Bihar Electricity Grid Code, 2026

In the matter of: Consultative paper on draft Bihar Electricity Grid Code 2026

Comments received on a draftDated 4 Sep 2026

Draft

Voltaic holds no final regulation made from this draft.

Comments received on the draft Bihar Electricity Grid Code, 2026 — Consultative Paper.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on berc.co.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is Prayas (Energy Group)'s written submission to the Bihar Electricity Regulatory Commission on the draft Bihar Electricity Grid Code 2026, forwarded to the Commission by BERC's secretary by email (p8) and dated 4 September 2026 (p13). It responds to the draft published on 7 August 2026 and is deliberately confined to coal-based thermal generators, arguing for better transparency and operational efficacy (p9).

Section 1 (pp9–10) argues that the draft's turndown and ramp-rate requirements for intra-state thermal units should be brought in line with the CEA's Flexible Operation Regulations — a lower technical minimum and higher ramp capability than the draft provides — and asks that these be tested in sustained-operation trials, with penalties for generators that miss the CEA phasing-plan timelines.

Section 2 (pp10–11) proposes that peak/off-peak hours and high/low demand seasons be defined on net load (after must-run solar and wind), that fixed-cost recovery be weighted toward high-demand peak periods, and that generators declare capability block-by-block for the next day. It refers to Table 1 (p11).

Section 3 (pp12–13) asks BERC to incorporate the MoP Late Payment Surcharge Rules Amendment 2024 (Rule 9) on sale of unrequisitioned surplus (URS) power, to have SLDC track and publish URS sales in a prescribed format (Table 2, p12), and to require monthly URS disclosure on generator websites.

Section 4 (p13) seeks SLDC transparency: monthly publication of generators that failed to demonstrate declared capability and incurred penalties, plus daily block-wise generation and ramping data for each scheduled generator. The submission closes by asking to be taken on record and for leave to make further submissions (p13).

Standard name
Grid Code
Primary topics
Grid operation and grid code, Scheduling and despatch, Power markets and exchanges

Read with this

Voltaic holds no final regulation made from this draft.

Proposed changes (drafts with no final yet)

One more document belongs here and is not on Voltaic: a draft or notice on a draft.

Voltaic last read BERC's website for final documents on 24 Nov 2026 and for drafts on 21 Nov 2026. A document BERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on berc.co.in ↗

Report an issue with this document