Skip to content

SSERC · Sikkim State Electricity Regulatory Commission

Grid Interactive Solar PV Systems Regulations, 2021 — Second Amendment, 2025

Sikkim State Electricity Regulatory Commission (Grid Interactive Solar PV Systems) (Second Amendment) Regulations, 2025

AmendmentDated 2 May 2025Published in the Gazette 3 Mar 2025No. 13/SSERC/2014-15/05 dated 02.05.2025

Amends the Grid Interactive Solar PV Systems Regulations, 2021.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on sserc.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the Second Amendment to the SSERC (Grid Interactive Solar PV Systems) Regulations, 2021, issued by the Sikkim State Electricity Regulatory Commission and published in the Sikkim Government Gazette (p1). It restates the short title, extent and commencement and the scope of application, then makes two substantive changes to the Principal Regulations.

Clauses 1 and 2 (p1) confirm that the amendments extend to the whole State of Sikkim and bind all distribution licensees and their consumers taking electricity at voltage levels up to 11,000 volts, including third-party-owned grid-interactive solar systems. The amendments come into force from Gazette publication.

Clause 3 (p1) substitutes sub-regulation (4) of Regulation 9 of the Principal Regulations, allocating responsibility for meter testing charges between the distribution licensee and the consumer, with the split turning on whether the consumer falls in the Domestic category.

Clause 4 (p2) inserts two new sub-regulations after the sub-regulation (6) inserted by the First Amendment Regulations, 2024. New sub-regulation (7) waives the application fee and security deposit for rooftop solar installations by Domestic category consumers under Regulation 11(1), (2) and (3). New sub-regulation (8) waives the connection agreement requirement under Regulation 11(1) and (2) for Domestic category consumers opting for net metering.

The practical effect is a consumer-facing relaxation concentrated on domestic rooftop solar: cheaper and simpler to apply, and no connection agreement for net metering. The document is two pages and is signed by the Commission's Secretary (p2).

Standard name
Net Metering and Rooftop Solar
Primary topics
Net metering, Metering, Security deposit

Read with this

Voltaic last read SSERC's website for final documents on 24 Nov 2026 (7 pages) and for drafts on 21 Nov 2026. A document SSERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on sserc.org ↗

Report an issue with this document