Skip to content

SSERC · Sikkim State Electricity Regulatory Commission

Grid Interactive Distributed Solar PV Systems Regulations, 2021 — Amendment, 2024

Sikkim State Electricity Regulatory Commission (Grid Interactive Distributed Solar PV Systems) (Amendment) Regulations, 2024

AmendmentDated 11 Jun 2024Published in the Gazette 12 Jun 2024No. 13/SSERC/2014-15/01 dated 11.06.2024

Amends the Grid Interactive Solar PV Systems Regulations, 2021.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on sserc.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

A two-page gazette notification by which the Sikkim State Electricity Regulatory Commission amends its 2021 regulations for grid-interactive distributed solar PV. It was signed on 11 June 2024 and published in the Sikkim Government Gazette (Extraordinary No. 306) on 12 June 2024, and comes into force from that publication date (p1).

Regulation 2 restates who the framework covers: distribution licensees in Sikkim and their consumers taking electricity at up to 11,000 volts, including grid-interactive solar systems owned by a third party (p1). This looks like a restatement of scope rather than a textual amendment of a numbered provision of the Principal Regulations.

The operative change is to Regulation 11 of the Principal Regulations, which governs the application and approval process. Two entries in the table of timelines in Regulation 11(1)(i) and (ii) — row 12, column 2 — are substituted with a period counted from the date of submission of the work completion report or installation report (p1–2). Regulation 11(2) is replaced so that the distribution licensee must publish Form 1(A), Form 1(B), the connection agreement formats and the installation certificate on its website and at its local offices (p2).

Two new sub-regulations are inserted after Regulation 11(3). New 11(4) gives deemed acceptance, without a technical feasibility study, to complete applications for solar systems up to 10 kW, and requires the licensee to carry out any commensurate enhancement of the consumer's sanctioned load. New 11(5) allocates responsibility for upgrading distribution infrastructure (service line, transformer capacity and the like) between the licensee and the consumer, with a proviso that for systems up to 10 kW the cost of strengthening distribution infrastructure, including the distribution transformer, is included in the licensee's revenue requirement (p2).

Standard name
Net Metering and Rooftop Solar
Primary topics
New connections and load changes, Capital cost and investment

Read with this

Voltaic last read SSERC's website for final documents on 24 Nov 2026 (7 pages) and for drafts on 21 Nov 2026. A document SSERC issued after the page that lists it was read may not be held by Voltaic yet.