MERC · Maharashtra Electricity Regulatory Commission
Approval of Capital Investment Schemes Regulations, 2022
Maharashtra Electricity Regulatory Commission (Approval of Capital Investment Schemes) Regulations, 2022
RegulationDated 12 Jul 2022No. MERC/Technical /Capex Regulations,2022/315
Summary
Summary written by software, from pages 1 to 72 of 100. Check the regulator's original before you rely on it.
The MERC (Approval of Capital Investment Schemes) Regulations, 2022 are a principal regulation of the Maharashtra Electricity Regulatory Commission, notified as No. MERC/Technical/Capex Regulations,2022/315 and signed at Mumbai on 12 July 2022 (p50), made under sections 61 and 86 read with section 181 of the Electricity Act, 2003 (p51). They extend to the whole of Maharashtra and bind existing and future generation businesses, transmission and distribution licensees, the STU, MSLDC and their successors — collectively 'Regulated Power Entities' — when they seek approval of capital investment (p51).
Regulation 1 covers title, extent, applicability and commencement from Gazette publication, and carves out the capital cost of new generating units and additional capitalisation within original scope to the MYT Regulations, 2019 (p51). Regulation 2 (pp51–55) defines terms including Capex, DPR and Non-DPR Schemes, Emergency Works, Useful Life, Prudence Check and Cost Benefit Analysis/Monitoring.
Regulation 3 (pp55–63) sets the objectives a scheme must serve, indicative eligible categories for generation, transmission, distribution and MSLDC, a list of works that will not be allowed as capex, the conditions for asset replacement, treatment of Opex Schemes, and a supplementary equipment useful-life table.
Regulation 4 (pp63–66) is the approval framework: a two-stage process of in-principle approval followed by final approval of completed cost, value thresholds separating DPR from Non-DPR schemes and tiered review, CISC scrutiny, quarterly filing and limits on clubbing or splitting schemes. Regulation 5 (pp66–69) prescribes the contents of an in-principle application and the narrow grounds for revised approval; Regulation 6 (pp70–71) prescribes the completed-cost application; Regulation 7 (p71) requires a Rolling Capital Investment Plan; Regulation 8 (p72) sets the prudence-check framework.
Read with this
Commencement notices and reasons
Procedures and orders made under it
Earlier drafts
- Dated 14 Mar 2022Approval of Capital Investment Schemes Regulations, 2022 — Draft
- Released with the notice dated 14 Mar 2022Explanatory memorandum: Draft Approval of Capital Investment Schemes Regulations, 2022 — Explanatory Memorandum
- Dated 14 Mar 2022Public notice: Draft Approval of Capital Investment Schemes Regulations, 2022 — Public Notice Inviting Comments
- Dated 5 Apr 2022Notice extending the date for comments: Extension of time for comments on Draft Capital Investment Schemes Regulations, 2022 — Public Notice
One more document belongs here and is not on Voltaic: a draft or notice on a draft not held as English text.
Voltaic last read MERC's website for final documents on 24 Nov 2026 (8 pages) and for drafts on 24 Nov 2026. A document MERC issued after the page that lists it was read may not be held by Voltaic yet.
As of its reading of MERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.