MERC · Maharashtra Electricity Regulatory Commission
Removal of Difficulty — DPR Submission under the Capex Approval Regulations, 2022
Removal of Difficulty in implementation of Regulation 4.21 of the MERC (Approval of Capital Investment Schemes) Regulations, 2022 for submission of Detailed Project Reports (DPRs)
OrderDated 26 May 2026
Made under the Approval of Capital Investment Schemes Regulations, 2022.
Summary
Summary written by software. Check the regulator's original before you rely on it.
MERC order dated 26 May 2026 granting a time-bound procedural relaxation to the quarterly DPR-submission framework for capital investment schemes. The Commission recalls that the MERC (Approval of Capital Investment Schemes) Regulations, 2022 came into force on 12 July 2022 and that Regulation 4.21 requires applicants to file DPR schemes for in-principle approval quarterly — by 30 April, 31 July, 31 October and 31 January (p1).
MSETCL, by representation dated 13 May 2026, asked to file monthly instead, citing heavy transmission expansion (EHV substations, corridor strengthening, STATCOM, RE evacuation), RE integration and STU/TBCB works, and arguing that the quarterly cycle delays approvals, forces cost revisions when the Schedule of Rates changes, and hampers execution (p1–2). MSETCL assured each DPR would still carry full technical justification, cost-benefit analysis and documentation (p2). The Commission also cites its MYT Order of 28 March 2025 in Case No 178 of 2024, where RE-evacuation schemes were capitalised ahead of DPR approval to keep RE evacuation unconstrained (p2–3).
Exercising Regulation 24 (Power to Remove Difficulties) of those Regulations (p3), the Commission allows RE evacuation DPRs to be submitted monthly, on or before 31 May, 30 June, 31 July and so forth, instead of quarterly; the dispensation runs only up to the quarter ending 30 April 2028; it covers only four categories of scheme (RE evacuation schemes, associated RE-integration transmission infrastructure, RE-linked grid strengthening, and schemes for RE pooling stations, RE parks, hybrid projects and storage integration) (p3). All DPRs must still comply with the 2022 Regulations including justification, cost-benefit analysis and supporting documents, and every non-RE scheme stays on the quarterly cycle (p4). The Commission stresses this is not a general exception for all capital investment schemes (p4).
Read with this
The regulation
- Dated 12 Jul 2022Approval of Capital Investment Schemes Regulations, 2022
Commencement notices and reasons
Earlier drafts
- Dated 14 Mar 2022Approval of Capital Investment Schemes Regulations, 2022 — Draft
- Released with the notice dated 14 Mar 2022Explanatory memorandum: Draft Approval of Capital Investment Schemes Regulations, 2022 — Explanatory Memorandum
- Dated 14 Mar 2022Public notice: Draft Approval of Capital Investment Schemes Regulations, 2022 — Public Notice Inviting Comments
- Dated 5 Apr 2022Notice extending the date for comments: Extension of time for comments on Draft Capital Investment Schemes Regulations, 2022 — Public Notice
One more document belongs here and is not on Voltaic: a draft or notice on a draft not held as English text.
Voltaic last read MERC's website for final documents on 24 Nov 2026 (8 pages) and for drafts on 24 Nov 2026. A document MERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.