WBERC · West Bengal Electricity Regulatory Commission
Cogeneration and Generation of Electricity from Renewable Sources of Energy (First Amendment) Regulations, 2020 — Draft
West Bengal Electricity Regulatory Commission (Cogeneration and Generation of Electricity from Renewable Sources of Energy) (First Amendment) Regulations, 2020
Draft amendmentDated 15 Sep 2020WBERC/Regulation-64/20-21 dated 15th September, 2020
Draft
A proposal that has since been finalised as the Cogeneration and Generation of Electricity from Renewable Sources of Energy Regulations, 2013 — First Amendment, 2020.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is a WBERC public notice (p1) that withdraws an earlier draft notification (No. WBERC/Regulation-64/20-21/5729 dated 11.06.2020) and puts out a fresh draft of the First Amendment to the Commission's 2013 Cogeneration and Renewable Sources Regulations. Stakeholders have until 25.09.2020, 5 P.M. to file suggestions and objections; copies of the draft and of the existing regulation are available at the Commission's office. The draft itself begins at p2 and is the substantive text.
The draft (p2) restates its short title, extends the amendment to the whole of West Bengal, and makes it effective on Gazette publication. It then rewrites the Principal Regulation's definition clause (pp2–3), inserting a definition of "eligible consumer" tied to rooftop/ground-mounted solar PV of a stated minimum size, and inserting definitions of net metering, net billing, net meter and the two connection agreements; it substitutes the definitions of renewable energy sources and of Renewable Purchase Obligation, and deletes two existing clauses.
The core is the RPO regime (pp3–5): a new regulation 3.0/3.1 sets a year-wise solar, non-solar and total purchase obligation trajectory for 2020-21 to 2022-23, with the base of computation, exclusions, and provisos on compulsory waste-to-energy procurement, cross-adjustment between solar and non-solar shortfalls, and continuation of existing consented PPAs. Later years' trajectories are left to a separate order; regulation 3.3 and 3.11 are deleted; and the routes for procuring renewable energy, advertising, and credit for open-access and rooftop generation towards a licensee's RPO are re-specified. Regulations 4.0 to 4.2 (pp5–6) cover non-compliance and confirm that fossil-fuel-based cogeneration does not count towards RPO; regulation 5.3 requires competitive bidding for solar power with listed exceptions.
Regulations 6.1(v)(c) and 7.2 (pp6–8) set who may connect rooftop solar, under which arrangement, capacity caps, interconnection, anti-islanding, metering and responsibility split. Regulations 8.0–8.2 and new 16.9 (p8) change terminology and require licensees to file a connectivity procedure. Schedules 1 and 2 (pp9–11) give the energy accounting and settlement methodology for net metering and net billing respectively.
Read with this
The regulation
Amendments and corrections
Commencement notices and reasons
- Dated 20 Dec 2020Statement of Reasons — RE First Amendment, 2020
Earlier drafts
Voltaic last read WBERC's website for final documents on 24 Nov 2026 and for drafts on 21 Nov 2026. A document WBERC issued after the page that lists it was read may not be held by Voltaic yet.