Wheeling and Retail Supply Tariff Regulations, 2011 — First Amendment, 2012 — Statement of Objects and Reasons

Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Wheeling Tariff and Retail Supply Tariff) (First Amendment) Regulations, 2012.

Statement of reasonsDated 30 Mar 2012No. HPERC/dis/479 dated 30th March, 2012

Replaced by Multi Year Wheeling Tariff & Retail Supply Tariff Regulations, 2023

See that regulation for the date it took effect and for anything it keeps in force.

The commission's reasons for the Wheeling and Retail Supply Tariff Regulations, 2011 or one of its amendments.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal, any proceedings before the Commission pertaining to the period prior to the commencement of the Control Period, including Petitions for True up of expenses, annual performance review, etc.”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on hperc.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is HPERC's Statement of Objects and Reasons for the HPERC (Terms and Conditions for Determination of Wheeling Tariff and Retail Supply Tariff) (First Amendment) Regulations, 2012, issued from Shimla on 30 March 2012 under file No. HPERC/dis/479 (p1). It explains why the Commission is amending its 2011 wheeling and retail supply tariff regulations: the distribution licensee currently recovers extra power purchase costs — fuel surcharge variations, purchases above or within the approved quantum, and revised generation and transmission tariffs — only at the true-up stage, roughly two years later, which the Commission says harms the licensee's finances and burdens consumers (p1).

The change is anchored in clause 4.5(h)(4) of the Tariff Policy, requiring speedy recovery of uncontrollable costs, and in APTEL's judgment of 11 November 2011 in OP No. 1 of 2011, which under section 121 of the Electricity Act directed state commissions to avoid routine regulatory assets and to put in place a fuel and power purchase cost adjustment mechanism under section 62(4) — preferably monthly and at least quarterly (p1–2).

Pages 2–5 record the consultation: the draft was published in the Rajpatra on 2 February 2012 and on the Commission's website, with a public notice on 11 February 2012 in The Tribune and Punjab Kesari inviting objections for 30 days (p2). Only HPSEB Ltd. responded. Its objections on treatment of incremental power procurement cost (14-A), the formula for computing incremental cost (14-B) and incremental cost per unit of consumption (14-C) are set out with the Commission's views (p2–5). The Commission accepts capping at the weighted average power exchange and bilateral purchase price and accepts extra purchases driven by higher-than-approved sales, but rejects unscheduled-interchange pass-through (p3).

The Commission says it broadly followed the Forum of Regulators' model distribution tariff regulation but deviated on the ceiling, limiting the annual implication of incremental power purchase adjustment to 6% of HPSEBL's ARR (p5), and directs that the draft be finalised and notified in the Official Gazette (p5).

Standard name
Wheeling and Retail Supply Tariff Regulations
Primary topics
Fuel and power purchase cost adjustment, ARR and true-up, Tariff determination

Read with this

The regulation

Voltaic last read HPERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document HPERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on hperc.org ↗

Report an issue with this document