Conduct of Business (12th Amendment) Regulations, 2022 — Finalisation Order

Himachal Pradesh Electricity Regulatory Commission (Conduct of Business) (12th Amendment) Regulations, 2022

OrderDated 21 Jul 2022Published in the Gazette 21 May 2022

Replaced by Conduct of Business Regulations, 2024

See that regulation for the date it took effect and for anything it keeps in force.

Read with the Conduct of Business Regulations, 2005.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal anything done or any action taken or purported to have been done or taken including any order or notice or notification made or issued or any instrument executed or direction given under the regulations so repealed shall be valid and shall be deemed to have been done or taken under the corresponding provisions of these Regulations.”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on hperc.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This short order closes out HPERC's Twelfth Amendment to its Conduct of Business Regulations, 2005 — the rules governing how the Commission runs its proceedings and what it charges for petitions. It records that the amendment regulations were issued on 20 May 2022 and gazetted on 21 May 2022, and that the draft was published for objections the same day with comments due 21 June 2022 (p1–2).

The stated purpose of the amendment is to create fee provisions for MYT Business Plan and Capital Investment Plan petitions, where the Commission found fees inadequate or unprescribed (p1). Only one stakeholder responded — HPSEBL, the distribution licensee — raising two points on those fees (p2).

The Commission rejects the request to reduce the MYT business plan fee, citing the volume of work, and accepts the request to cap the fee for additional Capital Investment Plans during the MYT period, but sets the cap as a percentage of proposed investment rather than the flat ceiling the licensee proposed (p2). No comments came on any other draft provision, so those are retained as published (p2). The order ends with the decision to finalise and notify the amendment regulations (p3); the operative fee schedule itself is not reproduced here.

Standard name
Conduct of Business Regulations
Primary topics
Fees payable to the Commission

Read with this

The regulation

Proposed changes (drafts with no final yet)

One more document belongs here and is not on Voltaic: a draft or notice on a draft.

Voltaic last read HPERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document HPERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on hperc.org ↗

Report an issue with this document