Terms and Conditions for Determination of Tariff Regulations, 2009 — Seventh Amendment, 2014

Rajasthan Electricity Regulatory Commission (Terms and Conditions for Determination of Tariff) (Seventh Amendment) Regulations, 2014

AmendmentDated 24 Feb 2014In force from 1 Apr 2014No. RERC/Secy/ Reg. -107 dated 24th February, 2014

Replaced by Terms and Conditions for Determination of Tariff Regulations, 2014

See that regulation for the date it took effect and for anything it keeps in force.

Amends a regulation Voltaic does not hold.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on rerc.rajasthan.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the Seventh Amendment to the Rajasthan Electricity Regulatory Commission's 2009 Tariff Regulations, notified in Jaipur on 24 February 2014 and brought into force from 1 April 2014 (p1). It is a biomass- and biogas-focused amendment: it extends the life of the earlier biomass/biogas regime, resets performance norms and fuel-price mechanics for FY 2014-15, and rewrites the grid-connectivity, drawal, transmission/wheeling and banking provisions for these generators.

Paragraphs 1–4 (p1) give the short title and commencement and make three small changes: biomass and biogas provisions continue in force up to FY 2014-15, biogas projects get a 20-year life entry in regulation 2, and the control period for biomass and biogas is extended to 31 March 2015.

Paragraph 5 (p2–3) replaces regulation 82(1)(a), setting out the year-wise energy tariff table for biomass plants built under the 1999 Government of Rajasthan policy and commissioned before 30.09.2008, and adds a new 82(3) allowing a biomass generator to switch from the REC mechanism to preferential tariff, using the generic tariff of the year of commissioning for the plant's remaining useful life.

Paragraph 6 (p3–5) amends regulation 83: it moves the biomass performance-parameter year to 2014-15, replaces the capital cost entries and biomass fuel price provision (with future revisions to be recommended by a State-level Committee), rewrites the metering point for biomass/biogas energy accounting, and inserts a new sub-regulation 8 with the full set of performance parameters for generic biogas tariff determination.

Paragraph 7 (p5–6) replaces regulation 84 with the variable-charge formulae for biomass and biogas and their respective fuel price inputs. Paragraph 8 (p6–7) replaces regulation 89 on grid connectivity charges and the feeder-wise capacity limits for power injection into the State grid.

Paragraphs 9–10 (p7–9) rewrite regulation 90 on energy drawn from the grid during shutdown and outages (quarterly set-off), kVArh charges, and transmission and wheeling charges for third-party sale and captive use. Paragraph 11 (p9–10) replaces regulation 92 on banking of energy for captive consumption within the State, including intimation, accounting, payment for unutilised banked energy and banking charges in kind. Paragraph 12 (p10) inserts a new regulation 135 empowering the Commission to deviate suo-motu from the regulations with recorded reasons.

Standard name
Tariff Regulations
Primary topics
Tariff determination, Renewable energy tariff, Energy banking

Read with this

Voltaic last read RERC's website for final documents on 24 Nov 2026. A document RERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on rerc.rajasthan.gov.in ↗

Report an issue with this document