Skip to content

APERC · Andhra Pradesh Electricity Regulatory Commission

Interim Balancing & Settlement Code for Open Access Transactions, 2006 — Second Amendment, 2014

~J:nRegulation may be calkd tfi~;A~dli~ Pradesh Electricity Regulatory Commiss\_ion (Interim B ·. cing & Settlement Code fur OperiA~ffl Transactions) Second Amendment Regulation, 2014.

AmendmentPublished in the Gazette 1 Apr 2014Regulation No.2 of 2!114 dated APRIL l, 2014

Amends the Interim Balancing and Settlement Code, 2006.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on aperc.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the APERC's Second Amendment to its 2006 Interim Balancing & Settlement Code for Open Access Transactions, published in the Andhra Pradesh Gazette on 1 April 2014 and given prospective effect from that publication date (p1–2). It is the sequel to the Government of Andhra Pradesh Solar Power Policy-2012 (GO Ms. No.39 of 26-09-2012, amended by GO Ms. No.44 of 16-11-2012) and to the First Amendment (Regulation No.1 of 2013, notified 02-05-2013) that had brought solar into the code as a renewable source; a draft was put on the Commission's website on 25-02-2014 and a public hearing held on 12-03-2014 (p1).

The operative part does three things (p2). First, it inserts a definition of "Banking" into the principal regulation below clause 2(c): banking is the facility by which unutilised or excess energy from wind, solar and mini-hydel generation is parked in a separate account during a billing month and dealt with under Appendix-3 (p2). Second, it adds a proviso to clause 10.3 so that under-drawals sourced from those three renewable sources are treated as input into banking (p2). Third, it substitutes Appendix-3 wholesale with fresh terms and conditions for the banking facility — the banking year, the form and basis of banking charges, the windows in which drawal from the bank is barred, a year-round bar on peak time-of-day drawal, what happens to energy left unutilised, the DISCOM's purchase of residual banked energy with its pricing benchmark and settlement deadline, carry-forward of late-financial-year credits, and the advance notice generators must give of time-block-wise withdrawal schedules (p2).

The practical effect is to give wind, solar and mini-hydel open access users a defined banking regime inside the settlement code, with the Commission rather than the licensees setting the commercial terms (p2).

Standard name
Balancing and Settlement Code
Primary topics
Energy banking, Open access

Read with this

Voltaic last read APERC's website for final documents on 24 Nov 2026 (2 pages) and for drafts on 21 Nov 2026. A document APERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on aperc.gov.in ↗

Report an issue with this document