MERC · Maharashtra Electricity Regulatory Commission

Scheme for Utilisation of Gas-Based Power Generation Capacity, FY 2015-16 & 2016-17

Scheme for utilisation of Gas based power generation capacity

Published with a draftDated 27 Mar 2015No. 4/2/2015-Th-I dated 27th March, 2015

Draft

Voltaic holds no final regulation made from this draft.

Published with the Implementation of Scheme for Utilization of Gas-based Power Generation Capacity Regulations, 2015 — Draft.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on merc.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a Ministry of Power Office Memorandum of 27 March 2015 conveying the President's sanction for a two-year scheme to bring India's idle gas-based generating capacity back into operation using imported spot RLNG bought through a government-run reverse auction (p1). It runs for FY 2015-16 and FY 2016-17 and is to be reviewed afterwards (p8).

Paras 1–4 set the frame. The gas fleet is split into 'stranded' plants that received no domestic gas and plants that received some domestic gas and ran at low PLF in April 2014–January 2015, each listed in an annexure (p1; pp11–14). Power System Development Fund (PSDF) support is budgeted for each year and apportioned between the two groups (p2). An Empowered Pool Management Committee (EPMC) chaired by the Special Secretary/Additional Secretary (Power) runs the scheme on operational matters (p2). Eligibility is limited to plants whose April 2014–January 2015 average PLF was below the target PLF, with the list declared before bidding (pp2–3).

Para 5 is the bargain at the heart of the document: central customs and service-tax relief, state VAT/CST/octroi/entry tax waivers, cuts in pipeline tariff, regasification charges and marketing margin, forfeiture of return on equity by stranded developers with fixed cost capped at debt service and O&M, gas swapping and co-mingling, a waiver of transmission charges and losses, PSDF support limited to incremental generation, and bank relief under RBI guidelines — all available only where the host State agrees to the tax waivers (pp3–5).

Paras 6–11 set the commercial parameters and process: indicative target PLF (differentiated by year and by monsoon/non-monsoon months) and indicative target prices for discoms, both adjustable by the EPMC within the PSDF outlay (pp5–6); GAIL as sole e-bid RLNG procurer, operating through GSPCL inside Gujarat (p6); a reverse e-bidding design in which bidders quote per-unit PSDF support and incremental units, ranked from the lowest, with ceiling prices and a cut-off when either the PSDF or the RLNG budget is exhausted (pp6, 17–18); release of PSDF money to discoms against CEA, GAIL, plant and discom certificates, with all cash flows through a lead-bank Trust & Retention account and support confined to incremental generation over base PLF (pp6–8); and MSTC as bid process manager at PSDF cost (pp8–9). The annexures carry the two plant lists, the revised customs waiver procedure, the gas swap arrangement and the bidding mechanism (pp11–19).

Primary topics
Fuel price and supply, Power System Development Fund (PSDF), Power procurement and PPAs

Read with this

Voltaic holds no final regulation made from this draft.

2 more documents belong here and are not on Voltaic: 2 drafts or notices on a draft not held as English text.

Voltaic last read MERC's website for final documents on 24 Nov 2026 (8 pages) and for drafts on 24 Nov 2026. A document MERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on merc.gov.in ↗

Report an issue with this document