Deviation Settlement Mechanism and Related Matters (First Amendment) Regulations, 2024 — Draft

Himachal Pradesh Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) (First Amendment) Regulations, 2024

Draft amendmentDated 23 Nov 2024HPERC-H(1)25/2021 dated the 23rd November, 2024

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on hperc.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

The Commission proposes to amend its Deviation Settlement Mechanism Regulations, 2024 and has published the draft for objections under s.181(3) of the Electricity Act. The preamble (p1) gives the reason: HPSLDC reported that the State's deviation bills ran a deficit that could not be recovered from the relevant intra-State entities because Regulation 10 of the principal Regulations caps the amount recoverable, and removing that cap requires amending Regulation 10(1)(ii) and Regulation 12(3).

Clause 2 (p2) substitutes Regulation 10(1)(ii) with a proportionate-recovery rule: where the deviation charges payable by State Entities for a day fall short of what the SLDC owes NRLDC/NRPC for the State as a whole, each entity's liability for that day is scaled up to cover the gap. The accompanying explanation requires the adjustment to be made daily, separately for each day and each set of charges, even though bills are raised weekly, and not to be netted against amounts receivable.

Clause 3 (p2–3) substitutes Regulation 12(3), which governs the SLDC's payment of amounts due to buyers and sellers from the State Deviation Pool Account — the payment window after receipts arrive, simple interest for delay, payment out of the pool balance (and pro rata from the Fund under Regulation 15) where an entity defaults beyond the stated period, and the continuance of the defaulter's interest liability even after the buyer/seller has been paid.

The draft is a consultation document: it will be taken up only after thirty days from publication of the notification in the Rajpatra, with objections or suggestions to the Secretary at the stated address; the text is also posted on the Commission's website (pp1–2).

Standard name
DSM Regulations
Primary topics
Deviation settlement (DSM), Energy accounting and settlement, Late payment surcharge and rebate

Read with this

Voltaic last read HPERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document HPERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on hperc.org ↗

Report an issue with this document