Renewable Energy Tariff, RPO and REC Regulations, 2017 — 1st Amendment, 2017

Haryana Electricity Regulatory Commission (Terms and Conditions for determination of Tariff from Renewable Energy Sources, Renewable Purchase Obligation and Renewable Energy Certificate) Regulations (1st Amendment), 2017

AmendmentDated 27 Aug 2018Regulation No. HERC/40/2018/1st Amendment/2018 dated The 27th August, 2018

Replaced by RE Tariff, RPO and REC Regulations, 2021

See that regulation for the date it took effect and for anything it keeps in force.

Amends the Terms and Conditions for determination of Tariff from Renewable Energy Sources, RPO and REC Regulations, 2017.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on herc.org.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a short, four-clause amendment by the Haryana Electricity Regulatory Commission to its 2017 regulations on renewable energy tariffs, renewable purchase obligation and renewable energy certificates. It is notified as Regulation No. HERC/40/2018/1st Amendment/2018, dated 27 August 2018, extends to the whole of Haryana, and comes into force on the date of notification in the Haryana Government Gazette — a date the text does not print (p1). The amendment is expressly partial.

Clause 2 substitutes Regulation 30, which governs capital cost, and sets out capital cost for biomass power projects differentiated by fuel — rice straw/stubble versus other fuels — and by cooling technology, water-cooled versus air-cooled condensers (p1–2). Clause 3 inserts a clarification after Regulation 60(2): it explains that the 500 MW cap is the aggregate installed capacity of solar PV projects commissioned in Haryana for consumption within Haryana that avail the waivers and concessions under these regulations; it lists what HVPNL weighs when granting connectivity (feasibility, date of project registration, financial closure); it makes HAREDA the nodal agency to monitor project milestones — installed capacity and location, capacity tied up for Haryana consumption, land acquisition, connectivity for open access, financial closure and commissioning date — through a website interface to be developed within two months; and it requires every developer wanting waivers to register the specific project with HAREDA before connectivity is granted (p2–3).

Clause 4 replaces the first paragraph of Regulation 58 on banking of RE power, allowing a generator, captive producer or consumer in the State to bank power on paying banking charges plus transmission and distribution technical losses, under a banking agreement with the concerned Discom (p3).

Standard name
Renewable Energy Tariff Regulations, RPO Regulations, REC Regulations
Primary topics
Renewable energy tariff, Capital cost and investment, Energy banking

Read with this

Voltaic last read HERC's website for final documents on 24 Nov 2026 (2 pages). A document HERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on herc.org.in ↗

Report an issue with this document