Forecasting, Scheduling and Deviation Settlement Procedure for Wind and Solar Generation, 2024

Procedure for implementation of Forecasting, Scheduling and Deviation Settlement of Wind and Solar Generation

ProcedureDate not stated

Made under the Forecasting, Scheduling and Deviation Settlement for Wind and Solar Generation Regulations, 2024.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on tnerc.tn.gov.in ↗

Summary

Summary written by software, from pages 1 to 51 of 55. Check the regulator's original before you rely on it.

This is the TNSLDC's implementation procedure for the TNERC (Forecasting, Scheduling and Deviation Settlement and Related Matters for Wind and Solar Generation) Regulations, 2024, approved by the Commission and to be read with the Regulations, IEGC, TNEGC, Intra State Open Access Regulations and amendments (pp1–3). It applies to wind and solar generators in Tamil Nadu, including hybrid systems, connected to the intra-State transmission or distribution system (including pooling substations) and using power for self-consumption or sale inside or outside the State; grid-interactive rooftop solar PV below 1 MW is excluded (p3). Commercial settlement—levy and collection of deviation charges—is to commence from 01-04-2024, with TNSLDC required to put DSM infrastructure in place first (p4).

Sections 2–7 assign responsibilities. A QCA appointed by majority generators (or by generators at a pooling substation or state level) must meet qualifying criteria on forecasting capability, experience, net worth, team and authorization (pp4–6). QCAs act as the single point of contact for TNSLDC, run 24x7 control centres, submit forecasts and schedules for wind and solar separately, handle meter data, de-pool deviation charges and indemnify TNSLDC (pp6–9). Generators must authorize a QCA, cannot appoint multiple QCAs for a PSS, have time-bound notice and re-appointment rules, and are responsible for intra-state commercial settlement (pp9–11). TNSLDC provides the web portal, scheduling, state DSM accounts, monthly DSM statements and true-up petitions (pp11–12). TANGEDCO/DISCOM and STU/Transmission Licensee have metering, AMR, data, nodal-officer and coordination duties (pp12–14).

Sections 8–10 set registration/de-registration of QCAs, fees and communication. Registration is online, PSS-wise or state-wide, with scrutiny, processing fees, hard-copy verification, undertaking and a flow chart; de-registration can be self-initiated, generator-initiated or default-driven (pp14–18). TNSLDC fees are as per the Regulations or Commission orders (pp18–19). Real-time data is to be transmitted using IEC-104 and AMR/SCADA arrangements (pp19–20).

Sections 11–16 are the operational core. They specify forecasting and scheduling at PSS/state aggregate level, day-ahead submission and intra-day revisions, aggregation rules and five pooling-substation configurations for intra-state, inter-state and mixed feeders (pp20–26). Energy accounting uses interface meter data in 15-minute blocks, correction factors, monthly meter readings and a 15-day discrepancy window (pp26–28). Deviation accounting computes absolute error and monthly DSM statements with timelines (pp28–29). Deviation charges are split into intra-state and inter-state methodologies, with pooling substations classified into four categories, annual capping and reconciliation rules (pp30–32). Inter-state sellers face a payment mechanism with bank account, 10-day payment, interest on delay, irrevocable Letter of Credit and encashment/non-scheduling consequences (pp32–33). Monitoring-compliance provisions list defaults and consequences, including revocation of QCA registration (pp33–34). Grievance redressal and removal-of-difficulties clauses follow (p35), and Section 19 makes the procedure additional to the Regulations, with the Regulations prevailing on inconsistency (pp35–36).

Annexures and formats run from p36 onward: authorization letter (Annexure I), forecast/revision formats (Annexure II), real-time telemetry list (Annexure III), registration application (Annexure IV), technical and PPA data formats, indemnity bond, undertaking and declaration (Annexures V–VI/VII). Later annexures are not available.

Standard name
Forecasting, Scheduling and DSM for Wind and Solar
Primary topics
Scheduling and despatch, Deviation settlement (DSM), Energy accounting and settlement

Read with this

One more document belongs here and is not on Voltaic: a copy in another language.

Voltaic last read TNERC's website for final documents on 29 Sep 2026 and for drafts on 24 Nov 2026. A document TNERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on tnerc.tn.gov.in ↗

Report an issue with this document