TNERC · Tamil Nadu Electricity Regulatory Commission
RE Curtailment Management Procedure for Wind and Solar Generation, 2024
detailed procedure for management of RE curtailment for wind and solar generation
ProcedureDated 6 Jun 2024
Made under the Forecasting, Scheduling and Deviation Settlement for Wind and Solar Generation Regulations, 2024.
Summary
Summary written by software. Check the regulator's original before you rely on it.
The Tamil Nadu Electricity Regulatory Commission approves a detailed procedure for managing curtailment of wind and solar generation, to be read with the TNERC Forecasting, Scheduling and Deviation Settlement Regulations, 2024 (pp5–6). The preamble explains the must-run status of RE under the IEGC and APTEL's Appeal No. 197 of 2019, notes that curtailment should be transparent, and records that the Forum of Regulators issued model guidelines in November 2022 (pp4–5). The procedure is issued under Regulation 15.3 of the 2024 F&S Regulations, whose notification is dated 22-01-2024, and is signed for the Commission on 06-06-2024 (pp5, 36).
Sections 2–3 state the objective — a framework for curtailment and restoration with minimum impact on RE — and make the procedure applicable to wind, solar and RE hybrid generators connected to the intra-state transmission and distribution systems, including pooling sub-stations and self-consumption or sale arrangements (p6). Section 4 defines core terms such as available capacity, congestion, curtailment, dedicated evacuation network, QCA, restoration and system operator (pp7–9).
Section 5 sets out the grid-security parameters and boundary conditions that may justify curtailment: operating frequency, state periphery volume limits, thermal technical minimum, transmission and transformer loading limits and voltage limits (pp9–11). Section 6 gives the curtailment protocol: general grounds, frequency management, transmission congestion relief, and maintenance of CERC volume limits at the state periphery, including a decision matrix linking deviation and frequency to curtailment (pp12–16).
Sections 7–8 cover implementation: SLDC/RLDC roles, instruction content, pro-rata curtailment across PSSs, pre- and post-curtailment communication, web-portal and logbook records, and the responsibilities of SLDC, STU/transmission licensees, RE generators, QCAs/Lead Generators and distribution licensees (pp17–26). Section 9 requires restoration once the trigger ceases, using first-out-first-in where practical (p26). Sections 10–11 prescribe data reporting, unique event codes and energy accounting for curtailment and restoration instructions (pp26–28). Section 12 provides compensation only for curtailment for reasons other than grid security, with computation methods for grid unavailability and other curtailment, and states who bears compensation (pp28–32). Sections 13–17 deal with non-compliance, disconnection and penalties, grievance redress, removal of difficulties, general review, and annexure formats (pp32–36).
Read with this
The regulation
Procedures and orders made under it
One more document belongs here and is not on Voltaic: a copy in another language.
Voltaic last read TNERC's website for final documents on 29 Sep 2026 and for drafts on 24 Nov 2026. A document TNERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.