CERC · Central Electricity Regulatory Commission
Transmission Planning Task Force Report, February 2016
Report of Task Force for giving input for Draft Regulations on Transmission Planning
Annexure or form of a draftReleased with the notice dated 26 Apr 2017
Draft
Voltaic holds no final regulation made from this draft.
Annexure or form of the Transmission Planning and other related matters Regulations, 2017 — Draft.
Summary
Summary written by software. Check the regulator's original before you rely on it.
The document is the February 2016 report of a CERC-constituted Task Force set up to give inputs for separate regulations on transmission planning (p1, p6). It explains why the Planning Code in the CERC (Indian Electricity Grid Code) Regulations, 2010 should be taken out and replaced by dedicated transmission planning regulations (p8, p43). The main report (pp6-18) covers the Task Force's constitution and terms of reference (p6-7), the current planning methodology and its difficulties (p9-10), the need for state and DISCOM participation and for matching intra-state systems with ISTS (p11-14), and the principles, procedure and criteria the new regulations should contain (p14-17). It records that a Central Study Team and Regional Study Team should be created to collect data and conduct studies, with CEA in the lead and CTU as coordinator (p15, p68, p93-94). It also proposes a review mechanism for plans (p17-18) and a timeline for information exchange (p18).
The bulk of the document is annexures and minutes: Appendix-I is the CERC Office Order constituting the Task Force (p19); Appendix-II contains the minutes of four meetings held between July and December 2015 and associated annexures (pp21-96). These include the CEA presentation on the planning process (pp31-38), participant lists (p30, p46, p52, p92), AEGCL's views on NER transmission (p53), and outlines of the proposed planning process and time-lines (pp68-70, pp93-95).
Two draft regulation texts are attached. The first, Annexure-V (pp97-109), and a later revised draft (pp110-120) both contain chapters on preliminary provisions, scope, objectives, nodal agency, roles of CEA, CTU, STUs, NLDC, RLDCs, SLDCs, generators, DISCOMs/bulk consumers/transmission licensees, and the Standing Committee; principles of planning; transmission planning criteria; procedure for planning; review; information exchange timelines; manpower deployment; software; monitoring; and dispute resolution (pp97-109, pp110-120). The drafts propose that CEA prepare a 20-year perspective transmission plan and CTU a five-year rolling Master Transmission Plan (p58, p75, p100-101), classify upgrades into reliability, economic, interconnection, international and public-policy categories (p59, p76, p101), and follow a three-tier consultation before approval (p61-63, p78-79, p104-105). The draft says it shall come into force from the date of publication, but no Gazette date is printed (p97, p110). The document also sets out unresolved GNA issues (pp65-67, pp82-84, pp107-109).
Read with this
Voltaic holds no final regulation made from this draft.
Proposed changes (drafts with no final yet)
- Dated 26 Apr 2017Transmission Planning and other related matters Regulations, 2017 — Draft
- Dated 30 Sep 2016Annexure or form: Committee Report on Transmission Planning, Connectivity, LTA, MTOA and Other Related Matters, 2016
- Dated 26 Apr 2017Public notice: Transmission Planning Draft Regulations, 2017 — Public Notice
- Released with the notice dated 26 Apr 2017Explanatory memorandum: Draft Transmission Planning and other related matters Regulations, 2017 — Explanatory Memorandum
- Dated 5 Jun 2017Notice extending the date for comments: Public Notice — Extension of comments deadline, Draft Transmission Planning and other related matters Regulations, 2017
One more document belongs here and is not on Voltaic: a draft or notice on a draft not held as English text.
Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.