Committee Report on Transmission Planning, Connectivity, LTA, MTOA and Other Related Matters, 2016

Report of the Committee to Review Transmission Planning, Connectivity, Long Term Access, Medium Term Open Access and other related issues

Annexure or form of a draftDated 30 Sep 2016

Draft

Voltaic holds no final regulation made from this draft.

Annexure or form of the Transmission Planning and other related matters Regulations, 2017 — Draft.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

On 30 September 2016 CERC posted for stakeholders the report of a committee it had set up to review transmission planning, connectivity, long-term access (LTA), medium-term open access (MTOA) and related matters (p1). The notice states that the Commission has not examined the report and will consider it while framing regulations on connectivity and access to inter-State transmission (p1). The report is dated September 2016 (p2), was chaired by Shri Mata Prasad with members from APTEL and CERC, and held 15 meetings in January–May 2016 (p5, pp33–34).

After front matter — committee constitution, acknowledgements, acronyms and contents (pp5–12) — the Executive Summary (pp13–29) lists recommendations for a Central Repository of Generators at CEA; transmission planning based on States' projected load/generation and merit-order operation rather than LTA; injection and withdrawal General Network Access (GNA); a CEA-chaired Validation Committee; GNA operationalisation and charge-sharing rules; continued separate connectivity; dedicated lines built by generators; application fees and an Access Bank Guarantee; exit/downscaling, delay and upstream/downstream payment rules; use of congestion charges through PSDF; reservation of flow-gate capacity for day-ahead collective transactions; and State demand-forecasting and committee measures (pp15–29).

Chapter 1 (pp30–35) traces the background: the 2009 Connectivity Regulations effective from 1.1.2010, the 2010 Sharing Regulations, HCPTC approvals, IPP difficulties and the 2014 Staff Paper that led to the Committee's terms of reference. Chapter 2 (pp36–51) reproduces the Staff Paper's diagnosis — issues raised by transmission planners, the system operator, generators and market participants — and the alternatives discussed, including Alternative-1 products (connectivity plus full or injection access) and Alternative-2 GNA, plus bank guarantee, delay/exit and power-market corridor proposals. Chapter 3 (pp52–84) summarises stakeholder answers to 12 Staff Paper questions, quoting named respondents. Chapter 4 (pp85–126) summarises issues and suggestions from invitees: CEA, CTU, POSOCO, MoP, STUs/DISCOMs, IPPs, power system experts and others.

Chapter 5 (pp127–134) gives the history and present state of transmission planning, from load-based planning before open access to the present LTA-driven process, and records market changes — shorter PPAs, power-exchange growth, backing down of costlier stations — that motivate reform. Chapter 6 (pp135–197) is the analysis and conclusions. It recommends GNA-based planning with STU demand/withdrawal projections, CTU/CEA system studies, validation, regulatory approval and mid-course correction; details injection/withdrawal GNA, captive plants, PPA registration and scheduling priority; treats connectivity, dedicated lines, start-up power and metering; sets application fees and Access Bank Guarantee mechanics; covers exit, delay, force majeure/change in law, and sharing of transmission charges; and addresses congestion charges, power-market corridor allocation, technical planning criteria and State committees. Annexure-I is listed as the CERC order constituting the Committee (p12); Annexure-II is headed “Process of GNA/Connectivity” (p199); the bibliography follows (p200).

Primary topics
Network planning and investment, Connectivity and GNA, Open access

Read with this

Voltaic holds no final regulation made from this draft.

Proposed changes (drafts with no final yet)

One more document belongs here and is not on Voltaic: a draft or notice on a draft not held as English text.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.