Draft Transmission Planning and other related matters Regulations, 2017 — Explanatory Memorandum

Draft Central Electricity Regulatory Commission (Transmission P lanning and other related matters) Regulations, 2017 — Explanatory M emorandum

Explanatory memorandum to a draftReleased with the notice dated 26 Apr 2017

Draft

Voltaic holds no final regulation made from this draft.

Explanatory memorandum to the Transmission Planning and other related matters Regulations, 2017 — Draft.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

The memorandum is CERC's rationale note for the draft CERC (Transmission Planning and other related matters) Regulations, 2017 (p1). It is not itself the regulations; it explains why the Commission proposes to replace the present connectivity/LTA-based planning approach with a planning framework built around General Network Access (GNA) (pp16-17, 21-24).

Part 1 traces the policy background: the Electricity Act 2003, Open Access in ISTS, the 2004 and 2009 Connectivity Regulations, the 2010 Sharing Regulations and the 2010 CTU approval regulations, followed by the September 2014 Staff Paper, a February 2016 Task Force report and a September 2016 Mata Prasad Committee report (pp1-2). It records CEA/CTU mandates under the Act and proposes deletion of the Planning Code in Part-3 of the Indian Electricity Grid Code, 2010 (pp3-4).

Part 2 lists the case for separate transmission planning regulations: defining roles, streamlining data exchange, aligning planning with markets and renewables, involving DISCOMs, monitoring implementation, reviewing plans, archiving data and ensuring trained manpower (p4).

Part 3 sets out the salient features: a Regional Study Committee in each region and a Central Study Committee at national level (pp5-6); a Central Repository of Generators in CEA to capture upcoming generation, including renewables (pp6-7); roles for CEA, CTU, STUs, system operators, generators and DISCOMs (p7); a proposed State Power Committee (p8); and a National Standing Committee on Transmission Planning in place of regional committees (p8).

It then explains transparency principles drawn from FERC Order 890 and Order 1000 (pp8-9), broad planning principles such as RES objectives, reactive power, right-of-way and cost-benefit analysis (pp9-10), and leaves study types to CEA's Transmission Planning Criteria while listing technical issues for those criteria (pp10-16).

Part 4 introduces GNA, distinguishing injection GNA and withdrawal GNA, with detailed modalities to follow in separate regulations (pp16-17). Part 5 compares the Staff Paper's Alternative-1 options with Alternative-2 GNA and reproduces the Mata Prasad Committee's reasoning on LTA, PPAs, shallow connection for renewables and withdrawal GNA (pp17-24). Part 6 describes how States would apply for GNA through STUs on a rolling multi-year basis (pp24-25). Part 7 covers renewable planning, Part 8 the frequency of standing committee meetings, Part 9 plan review and monitoring, and Part 10 manpower and certification for planning (pp25-28).

Primary topics
Network planning and investment, Connectivity and GNA, Grid operation and grid code

Read with this

Voltaic holds no final regulation made from this draft.

Proposed changes (drafts with no final yet)

One more document belongs here and is not on Voltaic: a draft or notice on a draft not held as English text.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.