Recovery of Expenditure for Providing New Connections Regulations, 2013 — First Amendment, 2020 — Statement of Reasons

West Bengal Electricity Regulatory Commission {Recovery of Expenditure for Providing New Connections) {First Amendment) Regulations, 2020

Statement of reasonsDate not stated

The commission's reasons for the Recovery of Expenditure for Providing New Connections Regulations, 2013 or one of its amendments.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on wberc.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is WBERC's Statement of Reasons (SoR) for the West Bengal Electricity Regulatory Commission (Recovery of Expenditure for Providing New Connections) (First Amendment) Regulations, 2020 — the instrument that changed how West Bengal distribution licensees charge for giving new connections. It is a consultation record, not the amendment itself: the operative regulation text is quoted inside it, and the amendment was finalised for notification in the Kolkata Gazette Extraordinary (p1–2).

Part 1 sets out the legal basis and the pre-publication process — a draft published on the Commission's website and advertised in five newspapers on 25.01.2020, with comments due by 10.02.2020 (p1). Part 2 explains the objective: supporting the state government's 'Ease of Doing Business' initiative by letting licensees give connections under a simple standard rate schedule rather than case-by-case estimates, and recalls the 2013 Principal Regulations being amended (p1).

Part 3 records that only CESC Limited responded (p2). Parts 4 and 5 take the two regulations the amendment touches one at a time — draft text, comments received, the Commission's reasoning, and the final text. Regulation 1 is the short title, extent and commencement clause (p2). Regulation 4.4 is the substantive change: licensees must fix service-connection rates in Rs/kVA or Rs/kW for applications at least up to 150 kVA of contract demand, with a procedure to be framed under the Standard of Performance Regulations (p2, p4). The Commission accepted CESC's request to allow Rs/kW alongside Rs/kVA, but declined to carve out housing, commercial and industrial complexes with multiple beneficiaries, pointing to that procedure and to later recovery of actual expenditure through consumers' bills (p3–4).

The SoR is signed by the Chairperson and two Members.

Standard name
Recovery of Expenditure and Miscellaneous Charges
Primary topics
Connection and miscellaneous charges, New connections and load changes, Supply to buildings and colonies

Read with this

Voltaic last read WBERC's website for final documents on 24 Nov 2026 and for drafts on 21 Nov 2026. A document WBERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on wberc.gov.in ↗

Report an issue with this document