CERC · Central Electricity Regulatory Commission
Transmission Licence Regulations — Statement of Reasons, 2009
In the matter of Regulations on procedure, terms and conditions for grant of transmission licence and other related matters
Statement of reasonsDated 26 May 2009
Replaced by Procedure, Terms and Conditions for Grant of Transmission Licence Regulations, 2024
See that regulation for the date it took effect and for anything it keeps in force.
The commission's reasons for the Procedure, Terms and Conditions for Grant of Transmission Licence Regulations, 2009 or one of its amendments.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is the Central Electricity Regulatory Commission's Statement of Reasons for its decisions on stakeholder comments received on the draft regulations on procedure, terms and conditions for grant of transmission licence and other related matters. The draft was published for comment by public notice dated 3.12.2008 (p1) and the persons who responded are listed in the Annexure (p20). It is an explanatory record, not the operative text: at p19 the Commission directs that the regulations be finalised on the basis of these observations and sent for publication in the Official Gazette.
Most of the document is a regulation-by-regulation walk-through. On definitions and eligibility, the Commission explains the newly inserted definition of a "state owned or controlled company" — letting one identified as project developer on or before 5.1.2011 be licensed without competitive bidding — and the reworked definition of "transmission plan", now tied to the National Electricity Policy (p1–3). It retains draft regulations 3 and 4 (competitive bidding and the Empowered Committee) as the link to the eligibility rule in regulation 7, and declines to broaden eligibility further (p3–4).
On procedure, it defends the application and public-notice regime in regulation 8 against suggestions to give the State Transmission Utility a role, to merge clauses, and to post objections and replies on the website; website posting is moved to before the application is made, and the Commission refuses to make public hearings mandatory, noting it holds hearings in practice (p5–8).
The remainder defends the post-grant regime: transmission charges under section 61 (p8); licence obligations — insurance across the whole licence term and compliance with NLDC/RLDC directions under the Electricity Rules, 2005 (p9–10); assignment of licence to a lenders' nominee (p10–11); term and renewal of licence (p11–12); inspection of accounts and reporting, with the Regional Power Committee added to regulation 18 (p12–13); alteration of licence terms at a beneficiary's instance (p14); and revocation, including a three-month notice, a natural-justice enquiry and a new clause for breach of the Transmission Service Agreement (p14–16). It closes with contravention notices and dispute resolution (p16–18), changes to Form I, and correction of a numbering error in the draft (p18–19).
Read with this
The regulation
Amendments and corrections
Commencement notices and reasons
Other copies of these documents (2)
Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.