MPERC · Madhya Pradesh Electricity Regulatory Commission
Constitution of Grid Code Review Committee and Functional Committees under the Madhya Pradesh Electricity Grid Code (Revision – III), 2024 — Order, 2024
In the matter of constitution of Grid Code Review Committee & Functional Committees as per Regulations No. 3.4 & 3.7 respectively of the Madhya Pradesh Electricity Grid Code (Revision – III), 2024.
OrderDated 23 Apr 2024
Made under the Madhya Pradesh Electricity Grid Code (Revision-III), 2024.
Summary
Summary written by software. Check the regulator's original before you rely on it.
MPERC's order of 23 April 2024 (p1) constitutes the standing committee machinery that the Madhya Pradesh Electricity Grid Code (Revision – III), 2024 requires. The Code was notified in the Madhya Pradesh Gazette on 15/03/2024, and Regulations 3.4 and 3.7 provide for a Grid Code Review Committee and Functional Committees respectively. The Commission had written to MPPTCL on 26/03/2024 asking for a proposal and asking stakeholders (MPPMCL, MPPGCL, Discoms, SLDC) to comply with the Code; MPPTCL filed its proposal on 12/04/2024 (p1).
Part A (p1) approves the Grid Code Review Committee — a high-level body chaired by the MPPTCL Managing Director, with the MDs of MPPGCL, MPPMCL, the three Discoms and MPNRED, the SLDC Chief Engineer, and members drawn from other transmission and distribution licensees, IPPs/CPPs/REGs of 50 MW and above, WRLDC (Grid India) and WRPC, plus a rotating representative of EHT/open access consumers at 132 kV and above.
Parts B to D (p2–3) constitute the three functional committees: the Operation and Co-ordination Committee chaired by the MP SLDC Chief Engineer; the Protection Co-ordination Committee chaired by MPPTCL's Chief Engineer (T&C); and the Transmission Metering Committee chaired by MPPTCL's Chief Engineer (Procurement). Each names its chairperson, a member secretary and convener, and the organisations represented — including rotating seats for solar and wind generators of 50 MW and above and seats for long-term open access customers and Indian Railways.
Clause 5 (p3) puts a continuing duty on each Chairperson and Convener to invite any member or stakeholder who has raised an issue before a meeting, so that objections and suggestions are addressed under the Code or other legislation in force.
Read with this
The regulation
- Dated 13 Mar 2024Madhya Pradesh Electricity Grid Code (Revision-III), 2024
Amendments and corrections
Other copies of these documents (1)
2 more documents belong here and are not on Voltaic: 2 copies in another language.
Voltaic last read MPERC's website for final documents between 24 Nov 2026 and 26 Nov 2026 (4 pages). A document MPERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.