Renewable Energy Purchase Obligation Regulations, 2010 — Amendment (RPO for 2015-16 to 2017-18)

Amendment to the Renewable Energy Purchase Obligation Regulation, 2010.

AmendmentDated 7 Mar 2016Published in the Gazette 30 Mar 2016TNERC/RPO/19-4 dated 07-03-2016

Replaced by Renewable Energy Purchase Obligation Regulations, 2023

See that regulation for the date it took effect and for anything it keeps in force.

Amends the Renewable Energy Purchase Obligation Regulations, 2010.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or purported to have been done under the repealed Regulations so far as it is not in consistent with these Regulations shall be deemed to have been or purported to have been done under these Regulations.”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on tnerc.tn.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is TNERC's amendment to its 2010 Renewable Energy Purchase Obligation Regulations, carried in the Tamil Nadu Government Gazette of 30 March 2016 (p1). It does one substantive thing: it inserts a new sub-regulation (1A) after regulation 3(1), fixing year-wise RPO targets for FY 2015-16, 2016-17 and 2017-18 — a total obligation rising from 9.50% to 14.00% of energy consumed, with a solar carve-out inside it rising from 0.50% to 5.00% (p2). An appended Explanation keeps the 2011-12 RPO level applicable to the Distribution Licensee for 2012-13, 2013-14 and 2014-15 (p2).

The remainder of the notification is context. The Explanatory Statement (p2–3) records that the Madras High Court has stayed the Regulation insofar as it includes open access and captive consumers, so that the Distribution Licensee is the obligated entity effectively being enforced against, and that enforcement on captive and open access consumers remains subject to the outcome of those cases and any other judicial forum (p3). It grounds the amendment in the Appellate Tribunal for Electricity's order of 20 April 2015 in O.P. No.1 of 2013, which directed State Commissions to fix RPO targets before the Multi Year Tariff period begins, and in the Ministry of New and Renewable Energy's enhanced solar capacity target (p2–3).

Pages 3–5 carry the standard statement showing the existing provision and the provision as amended, reproducing regulation 3 with the new sub-regulation (1A) table.

Standard name
RPO Regulations
Primary topics
Renewable purchase obligation (RPO / RCO)

Read with this

Voltaic last read TNERC's website for final documents on 29 Sep 2026 and for drafts on 24 Nov 2026. A document TNERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on tnerc.tn.gov.in ↗

Report an issue with this document