Renewable Energy Sources (Wind and Solar) Tariff Determination (First Amendment) Regulations, 2015

Rajasthan Electricity Regulatory Commission (Terms and Conditions for Determination of Tariff for Renewable Energy Sources - Wind and Solar Energy) (First Amendment) Regulations, 2015.

AmendmentDated 18 Mar 2015In force from 1 Apr 2015No.RERC/Secy./Regulation - 111 dated 18th March, 2015

Replaced by Terms and Conditions for Tariff Determination from Renewable Energy Sources Regulations, 2020

See that regulation for the date it took effect and for anything it keeps in force.

Amends the Terms and Conditions for Determination of Tariff for Renewable Energy Sources - Wind and Solar Energy Regulations, 2014.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on rerc.rajasthan.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

A single-page notification from the Rajasthan Electricity Regulatory Commission amending its 2014 renewable energy tariff regulations. It substitutes sub-regulation (2) of regulation 9 of the RERC (Terms and Conditions for Determination of Tariff for Renewable Energy Sources – Wind and Solar Energy) Regulations, 2014, so that the discount factor used for levellised tariff computation must be equivalent to the post-tax weighted average cost of capital (p1). That is the whole operative content: one sub-regulation replaced, with the rest of the 2014 parent regulation untouched.

The regulation is issued under s.86(1)(e) read with s.181 of the Electricity Act, 2003, after previous publication and consideration of stakeholder views (p1). It is dated 18 March 2015 and comes into force on 1 April 2015 (p1) — from the start of the 2015-16 financial year, so it governs prospective levellised tariff determinations rather than reopening anything already determined.

For an analyst, this matters only as a pointer: the live discount-factor rule for Rajasthan wind and solar levellised tariffs sits in regulation 9(2) of the 2014 parent regulation as substituted here, not in the parent's original text.

Standard name
Renewable Energy Tariff Regulations
Primary topics
Renewable energy tariff, Tariff determination, Return, financing and working capital

Read with this

Voltaic last read RERC's website for final documents on 24 Nov 2026. A document RERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on rerc.rajasthan.gov.in ↗

Report an issue with this document