TSERC · Telangana State Electricity Regulatory Commission
Licensee's Duty for Supply of Electricity on Request Regulation, 2013 — Third Amendment, 2026 — Draft
TELANGANA ELECTRICITY REGULATORY COMMISSION (LICENSEE'S DUTY FOR SUPPLY OF ELECTRICITY ON REQUEST) DRAFT THIRD AMENDMENT REGULATION, 2026
Public notice on a draftDated 19 Feb 2026
Draft
The draft has since been finalised as the Licensee's Duty for Supply of Electricity on Request Regulation, 2013 — Third Amendment, 2026.
Public notice on the Licensee's Duty for Supply of Electricity on Request — Third Amendment, 2026 — Draft.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is a TGERC public notice opening stakeholder consultation on a draft Third Amendment to the Commission's (Licensee's Duty for Supply of Electricity on Request) Regulation No. 04 of 2013 (p1).
It first recites the background: to simplify and speed up release of LT service connections and additional loads in electrified areas, the Commission had notified the Second Amendment (Regulation No. 01 of 2026) on 19.01.2026, introducing uniform, objective, load-based service line charges that avoid individual site inspections and case-by-case estimation (p1). The Telangana DISCOMs have now asked for the same treatment to be extended to HT service connections at 11 kV and 33 kV (p1).
The Commission states it considers this appropriate, and expressly reserves the right to add to or amend the draft — including increasing or decreasing the proposed HT service line charges — after considering stakeholder and licensee suggestions (p1).
The draft is hosted on the Commission's website, and comments, in the prescribed format, must reach the Commission Secretary by 5:00 PM on 12.03.2026, in writing or by email (p2). The notice is dated Hyderabad, 19.02.2026 (p2).
Read with this
Voltaic does not hold the regulation itself.
Amendments and corrections
Other copies of these documents (1)
Earlier drafts
Voltaic last read TSERC's website for final documents on 24 Nov 2026 and for drafts on 21 Nov 2026. A document TSERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.