Skip to content

RERC · Rajasthan Electricity Regulatory Commission

Electricity Supply Code and Connected Matters, 2004 — Sixth Amendment, 2007

The Rajasthan Electricity Regulatory Commission (Electricity Supply Code and Connected Matters) (Sixth Amendment) Regulations, 2007

AmendmentDated 22 Jan 2007No. RERC/Secy/Reg. 61- dated 22 January, 2007

Replaced by Electricity Supply Code and Connected Matters Regulations, 2021

See that regulation for the date it took effect and for anything it keeps in force.

Amends a regulation Voltaic does not hold.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on rerc.rajasthan.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the Rajasthan Electricity Regulatory Commission's Sixth Amendment to its Electricity Supply Code and Connected Matters Regulations, 2004, notified at Jaipur on 22 January 2007 (p1). It is a short, two-clause amendment confined entirely to agriculture-category connections; the rest of the 2004 Code is untouched.

Clause 1 gives the title and says the regulations come into force from publication in the official gazette — the gazette date is not printed in the text (p1).

The first amendment substitutes sub-clause 40(1)(3)(a) (p1–2). It fixes the window within which an application to restore an agriculture connection will be considered, drawing a distinction between disconnections effected before and after 30.6.2004, and provides that an applicant outside the window is treated as a new applicant. Where the application is in time, the consumer must pay reconnection charges together with the dues outstanding at the time of disconnection and compound interest, and, for disconnections exceeding two years where the line has been removed, a per-HP charge in two load slabs (p2).

The second amendment adds a sub para to the schedule entry dealing with additional amounts to be deposited for agriculture connections: where the demand under the revised Agriculture Policy exceeds what the applicant has already deposited, the difference is recovered from the applicant or consumer (p2).

The stated trigger for the amendment is the State Government's further amendment of its Agriculture Policy of 18.9.2004 by directive dated 22.6.06 (p1). The notification is signed by the Commission's Secretary (p2).

Standard name
Electricity Supply Code
Primary topics
Agricultural supply, Connection and miscellaneous charges, New connections and load changes

Read with this

Voltaic does not hold the regulation itself.

Consolidated copies, for reference (1)

Voltaic last read RERC's website for final documents on 24 Nov 2026. A document RERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on rerc.rajasthan.gov.in ↗

Report an issue with this document