Renewable Energy Obligation Regulations, 2007 — Fifth Amendment, 2019

Rajasthan Electricity Regulatory Commission (Renewable Energy Obligation) (Fifth Amendment) Regulations, 2019

AmendmentDated 11 Jan 2019No. RERC/Secy/Regulation- 125 dated January 11, 2019

Replaced by Rajasthan Renewable Purchase Obligation Regulations, 2023

See that regulation for the date it took effect and for anything it keeps in force.

Amends the Rajasthan Renewable Energy Obligation Regulations, 2007.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal anything done or action taken or purported to have been done for the purpose of meeting RE obligation shall be deemed to have been done or taken under the corresponding provisions of these Regulations.”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on rerc.rajasthan.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

The Rajasthan Electricity Regulatory Commission's Fifth Amendment to its Renewable Energy Obligation Regulations, 2007, issued at Jaipur on 11 January 2019 as notification No. RERC/Secy/Regulation-125 (p1). It does one thing: it restates the renewable purchase obligation (RPO) for FY 2018-19 through FY 2023-24, with the revised 2018-19 obligation backdated to 1 April 2018 and the remainder coming into effect on 1 April 2019 (p1).

Three tables are inserted into or substituted for Regulation 4 of the Principal Regulations. Under sub-regulation (2)(A) a multi-year trajectory showing non-solar, solar and total RPO as percentages of energy is added, with two provisos allowing a shortfall in one category to be met by excess purchase of the other once compliance with the first has reached 80% (p1–2). Under (2)(B) the same trajectory is restated as a single percentage of energy consumption, on a basis that excludes consumption met from hydro sources (p2). Sub-regulation (3) is replaced with a distribution-licensee obligation disaggregated across wind, hydro, biomass, solar and total; it defines what falls in the biomass category, lets a biomass shortfall be made good by wind (raising the wind obligation accordingly), and repeats the 80% interchangeability provisos (p2–3).

A closing note records the Principal Regulations and the four earlier amending regulations with their gazette publication dates (p3). The disaggregated obligation is expressly imposed on distribution licensees including deemed licensees; the text does not restate which other categories of obligated entity the other tables bind.

Standard name
RPO Regulations
Primary topics
Renewable purchase obligation (RPO / RCO)

Read with this

Voltaic last read RERC's website for final documents on 24 Nov 2026. A document RERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on rerc.rajasthan.gov.in ↗

Report an issue with this document