HERC · Haryana Electricity Regulatory Commission
RE Tariff, RPO and REC Regulations, 2021 — 3rd Amendment, 2025
Haryana Electricity Regulatory Commission (Terms and Conditions for determination of Tariff from Renewable Energy Sources, Renewable Purchase Obligation and Renewable Energy Certificate) Regulations, 2021, (3rd Amendment) 2025
AmendmentDated 29 Oct 2025Published in the Gazette 4 Nov 2025In force from 1 Apr 2025HERC/53/2021/3rd Amendment/2025 dated The 29th October, 2025
Replaced by Renewable Energy Tariff, RPO and REC Regulations, 2025
See that regulation for the date it took effect and for anything it keeps in force.
Amends the RE Tariff, RPO and REC Regulations, 2021.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is a one-page HERC notification amending the Commission's 2021 regulations on renewable energy tariffs, renewable purchase obligation and renewable energy certificates. It was issued on 29 October 2025 and published in the Haryana Government Gazette on 4 November 2025, but is stated to come into force with effect from 1 April 2025 — i.e. retrospectively (p1).
It has only two printed clauses. Clause 1 gives the short title, commencement and extent: the amendment reaches "all grid connected renewable energy projects and obligated entities in the State of Haryana" (p1). Clause 4 substitutes the first paragraph of Regulation 4 of the principal regulations, restating the Control Period or Review Period as FY 2021-22 to FY 2025-26 rather than extending it, and providing that FY 2025-26 fuel cost, O&M and capital cost are to be derived by escalating the corresponding FY 2024-25 (or, for capital cost, the FY 2021-22 to FY 2024-25) figures by a stated annual escalation factor (p1).
No savings or repeal clause, schedules or annexures appear.
Read with this
The regulation
- Dated 30 Apr 2021RE Tariff, RPO and REC Regulations, 2021
Amendments and corrections
Voltaic last read HERC's website for final documents on 24 Nov 2026 (2 pages). A document HERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.